Claim No: CFI 020/2014

THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS

 

IN THE COURT OF FIRST INSTANCE

BETWEEN

GFH CAPITAL LIMITED

                                                                                          Claimant

and

DAVID LAWRENCE HAIGH

Defendant


  AMENDED ORDER OF H.E JUSTICE SHAMLAN AL SAWALEHI


UPON reviewing the Claimant’s Application Notice CFI-020-2014/10 dated 14 January 2015 (the “Application”) seeking an extension to the date for filing the Claimant’s Reply to the Defendant’s Defence until after the Case Management Conference (the “CMC”) listed on 2 February 2015 before H.E. Justice Shamlan Al Sawalehi, with the revised date for filing the Claimant’s Reply to be determined at the CMC.

AND UPON reading the relevant material in the case file

AND UPON reading the First Witness Statement of Tiernan Fitzgibbon dated 13 January 2015 and the exhibit attached thereto

AND UPON reviewing the letter from the Defendant’s representatives dated 15 January 2015 agreeing to the Claimant’s proposal to file their Reply to Defence after the CMC is concluded

AND HAVING considered Rule 16.18 of the Rules of the DIFC Courts (RDC)

AND PURSUANT to Rule 36.40 of the Rules of the DIFC Courts, paragraph 2 of this Order is amended.

IT IS HEREBY ORDERED THAT:

  1. The Application is dismissed as the Claimant has failed to provide sufficient reasons as to why an extension should be granted pursuant to RDC 16.18.
  2. The Claimant shall file their Reply to Defence by no later than 4pm on Thursday 29 January 2015.

 

Issued by:

Maha AlMehairi

Judicial Officer

Date: 18 January 2015

Re-issued on: 19 January 2015

At: 2pm

X

Privacy Policy

The Dispute Resolution Authority and all its affiliates are committed to preserve the confidentiality, integrity and availability of client data and personal information.

Dispute Resolution Authority and all its affiliates employees, vendors, contract workers, shall follow Information Security Management System in all the processes and technology.

  1. DRA's Top Management is committed to secure information of all our interested parties.
  2. Information security controls the policies, processes, and measures that are implemented by DRA in order to mitigate risks to an acceptable level, and to maximize opportunities in order to achieve its information security objectives.
  3. DRA and all its affiliates shall adopt a systematic approach to risk assessment and risk treatment.
  4. DRA is committed to provide information security awareness among team members and evaluate the competency of all its employees.
  5. DRA and all its affiliates shall protect personal information held by them in all its form.
  6. DRA and all its affiliates shall comply with all regulatory, legal and contractual requirements.
  7. DRA and all its affiliates shall provide a comprehensive Business Continuity Plan encompassing the locations within the scope of the ISMS.
  8. Information shall be made available to authorised persons as and when required.
  9. DRA’s Top Management is committed towards continual improvement in information security in all our processes through regular review of our information security management system.