Skip to Content

CFI 004/2014 Sonia Guetat v Mirabaud (Middle East) Ltd

CFI 004/2014 Sonia Guetat v Mirabaud (Middle East) Ltd

March 25, 2015

image_pdfimage_print

Claim No. CFI 004/2014

 

THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS

 

IN THE COURT OF FIRST INSTANCE

 

BETWEEN

 

SONIA GUETAT

Claimant

 

and 

 

MIRABAUD (MIDDLE EAST) LTD

Defendant


  CASE MANAGEMENT ORDER


UPON reviewing the Court file

AND UPON agreement by the Parties

IT IS HEREBY ORDERED BY CONSENT THAT

List of Issues

1. The Parties to agree a comprehensive list of factual and legal issues no later than 4pm on Sunday, 5 April 2015, which will serve as the basis of the claims that the Court has to determine. This is to replace the need for amendments to the Statements of Case.

Production of Documents

2. Further Standard production to be made by each party on or before 4pm on Sunday, 5 April 2015.

3. Parties to file and serve any Request to Produce on or before 4pm on Sunday, 5 April 2015.

4. Objections to Requests to produce (if any) shall be filed and served within 7 days thereafter and in any event not later than 4pm on Sunday, 12 April 2015.

5. Where objections to any Requests to Produce have been made, the Court will determine those objections on paper no later than 4pm on Thursday, 16 April 2015.

Witness Statements of Fact

6. Signed statements of witnesses of fact and hearsay notices, where required, to be exchanged by no later than 4pm on Thursday, 23 April 2015.

7. Any witness statement in reply to be filed and served within 1 week thereafter and in any event not later than 4pm on Thursday, 30 April 2015.

Trial Bundles

8. Agreed trial bundles to be completed in accordance with Part 35 of the RDC and lodged by no later than 4pm on Sunday, 3 May 2015.

Reading List

9. A single reading list approved by all Parties’ legal representatives for trial to be lodged with the Registry by no later than 4 pm on Thursday, 7 May 2015, together with an estimate of time required for reading.

Skeleton Arguments, Opening Statements and Chronology

10. Skeleton Arguments and Written Opening Statements to be mutually exchanged and lodged with the Court by no later than 4 pm on Thursday, 7 May 2015.

11. Parties to prepare a Chronology of significant events cross-referenced to significant documents, pleadings and witness statements, to be agreed, insofar as possible, and to be filed by no later than 4 pm on Thursday, 7 May 2015.

Pre-Trial

12. A Pre-Trial Review is to be fixed for hearing on 3 May 2015.

Trial

13. The trial of this matter is listed on 10 May 2015 with an estimated duration of two days.

Miscellaneous

14. Costs in the case.

15. Liberty to apply.

 

Issued by:

Natasha Bakirci

Assistant Registrar

Date of issue: 25 March 2015

At: 12pm

X

Privacy Policy

The Dispute Resolution Authority and all its affiliates are committed to preserve the confidentiality, integrity and availability of client data and personal information.

Dispute Resolution Authority and all its affiliates employees, vendors, contract workers, shall follow Information Security Management System in all the processes and technology.

  1. DRA's Top Management is committed to secure information of all our interested parties.
  2. Information security controls the policies, processes, and measures that are implemented by DRA in order to mitigate risks to an acceptable level, and to maximize opportunities in order to achieve its information security objectives.
  3. DRA and all its affiliates shall adopt a systematic approach to risk assessment and risk treatment.
  4. DRA is committed to provide information security awareness among team members and evaluate the competency of all its employees.
  5. DRA and all its affiliates shall protect personal information held by them in all its form.
  6. DRA and all its affiliates shall comply with all regulatory, legal and contractual requirements.
  7. DRA and all its affiliates shall provide a comprehensive Business Continuity Plan encompassing the locations within the scope of the ISMS.
  8. Information shall be made available to authorised persons as and when required.
  9. DRA’s Top Management is committed towards continual improvement in information security in all our processes through regular review of our information security management system.