Case Information
| Case number | CFI-008-2007 |
| Citation number | [2009] DIFC CFI 002 |
| Case title | CFI 008/2007 - Order |
| Claimant (S) | Ithmar Capital |
| Defendant (S) | 8 Investment Inc & Others |
| Keywords | -- |
| Case reference | -- |
| Judges | -- |
| Judgement summary | -- |
Judgement and Order
CFI 008/2007 - Order | DIFC Courts
Case No. CFI 008/2007
THE JUDICIAL AUTHORITY OF THE DUBAI INTERNATIONAL FINANCIAL CENTRE
IN THE COURT OF FIRST INSTANCE
Between
| ITHMAR CAPITAL | Claimant |
| and8 INVESTMENT INC | 1st Defendant |
| and8 INVESTMENT GROUP FZE | 2nd Defendant |
ORDER
UPON READING the application filed by the Claimant on 29 December 2008,
1. The witness examination application will be heard on 20 January 2009.
2. The Claimant to submit to the Court and Defendants a draft list of questions for the witness by 8 January 2009.
3. The Defendant to serve its skeleton argument by 15 January 2009.
4. Other outstanding applications will be heard before the examination application. Those other applications must be identified by not later than 8 January 2009 and the applicant must in the case of each such application serve a skeleton argument by that date if it has not yet done so. The respondent must serve its skeleton arguments by 14 January 2009.
Amna Al Owais
Date of Issue: 05 January 2009
At 09:30 am