Case Information
| Case number | CFI-004-2007 |
| Citation number | [2009] DIFC CFI 056 |
| Case title | CFI 004/2007 - Order |
| Claimant (S) | Arabtec Construction LLC |
| Defendant (S) | Ultra Fuji International LLC |
| Keywords | -- |
| Case reference | -- |
| Judges | -- |
| Judgement summary | -- |
Judgement and Order
Claim No: CFI 004/2007
THE JUDICIAL AUTHORITY OF THE DUBAI INTERNATIONAL FINANCIAL CENTRE
IN THE COURT OF FIRST INSTANCE
Between
| ARABTEC CONSTRUCTION LLC | Claimant/Receiving Party |
| Defendant/Paying Party |
ORDER
Pursuant to Part 36.40 of the Rules of the DIFC Courts, this Order is issued in replacement of the Order dated 11th June 2009 at 2:00pm due to an accidental slip in the full amount due to the Claimant/Receiving Party.
Upon Claimant/Receiving Party's request for a Default Costs Certificate dated 9 June 2009 and based on Claimant/Receiving Party's certifications that the Defendant/Paying Party has not served points of dispute within the required 21 day period in accordance with Part 40.15 of the Rules of the DIFC Courts:
IT IS ORDERED THAT:
Mark Beer
Date of Issue: 11th June 2009
at 4:00pm