Case Information
| Case number | CFI-016-2009 |
| Citation number | [2010] DIFC CFI 037 |
| Case title | CFI 016/2009 - Consent Order |
| Claimant (S) | Petra Invest Ltd |
| Defendant (S) | Shuaa Capital PSC |
| Keywords | -- |
| Case reference | -- |
| Judges | -- |
| Judgement summary | -- |
Judgement and Order
CFI 016/2009 - Consent Order | DIFC Courts
Claim No: CFI 016/2009
THE JUDICIAL AUTHORITY OF THE DUBAI INTERNATIONAL FINANCIAL CENTRE
IN THE COURT OF FIRST INSTANCE
BETWEEN:
| PETRA INVEST LIMITED | Claimant |
| andSHUAA CAPITAL PSC | Defendant |
| andMOHAMED ABDEL-KHALEQ MOHAMMED ABU-AL HAJ | Proposed Third Party |
CONSENT ORDER
IT IS ORDERED BY CONSENT:
1. The Claimant and the Defendant having agreed to the terms set out in the Schedule hereto it is ordered that all further proceedings in this claim be stayed except for the purpose of carrying such terms into effect.
2. The parties are at liberty to apply in order to carry out such terms into effect.
3. The Schedule to this Order is not to be disclosed without further order of the Court.
Mark Beer
Date of Issue: 16 May 2010
At: 4pm