Case Information

Case numberCFI-014-2010
Citation number[2011] DIFC CFI 014
Case titleCFI 014/2010 - Order
Claimant (S)Taaleem PJSC
Defendant (S)Deyaar Development PJSC,National Bonds Corporation PJSC
Keywords--
Case reference--
Judges--
Judgement summary--

Judgement and Order

CFI 014/2010 - Order | DIFC Courts

Claim No. CFI 014/2010

 

THE JUDICIAL AUTHORITY OF THE DUBAI INTERNATIONAL FINANCIAL CENTRE

 

IN THE COURT OF FIRST INSTANCE

 

BETWEEN

 

TAALEEM P.J.S.C.Claimant/First Respondent

And

 

(1) NATIONAL BOND CORPORATION P.J.S.C.

First Defendant/ Appellant

(2) DEYAAR DEVELOPMENT P.J.S.C.

Second Defendant/ Second Respondent

 

ORDER

 

UPON hearing of the First Defendant/Appellant's Application Number 088/2010

 

AND UPON hearing counsel for the First Defendant/ Appellant and the Claimant/ first Respondent;

 

IT IS ORDERED THAT:

 

1. This Application is dismissed

 

2. The First Defendant/ Appellant pays the Claimant/ First Respondent's costs of and occasioned by the Application, such costs to be the subject of detailed assessment if not agreed.

 

3. The date for the hearing of the appeal shall be 21 March 2011 to commence at 9.30am (U.A.E time).

 

4. The First Defendant/ Appellant shall have permission to submit a supplementary skeleton argument by 4pm (U.A.E time) on 7 March 2011.

 

5. The Claimant/First Respondent and the Second Defendant/Second Respondent each have permission to submit a supplementary skeleton argument by 4pm (UAE time) on 14 March 2011.

 

Issued by

Mark Beer

Registrar

Date of Issue: 8 March 2011

At: 12pm