Case Information
| Case number | CFI-024-2010 |
| Citation number | [2011] DIFC CFI 022 |
| Case title | CFI 024/2010 - Order |
| Claimant (S) | Corinth Pipeworks SA |
| Defendant (S) | Barclays Bank PLC |
| Keywords | -- |
| Case reference | -- |
| Judges | -- |
| Judgement summary | -- |
Judgement and Order
CFI 024/2010 - Order | DIFC Courts
Claim No: CFI 024/2010
THE JUDICIAL AUTHORITY OF THE DUBAI INTERNATIONAL FINANCIAL CENTRE
IN THE COURT OF FIRST INSTANCE
IN THE MATTER OF
| CORINTH PIPEWORKS S.A. | Claimant/ Respondent |
| and BARCLAYS BANK PLC | Defendant/ Applicant |
ORDER OF DEPUTY CHIEF JUSTICE SIR ANTHONY COLMAN
UPON reading the Application Notice 081/2010 and evidence filed by the Defendant on 28 October 2010 (the "Application")
AND UPON reading the Claim Form filed by the Claimant on 29 September 2010
AND UPON hearing counsel for the Defendant and the Claimant at the Application Hearing held on 17 January 2011 before Deputy Chief Justice Sir Anthony Colman
IT IS HEREBY ORDERED BY CONSENT THAT:
1. The Defendant is entitled to a declaration that the Court has no jurisdiction to try the claim.
2. The claim is struck out.
3. The Claimant shall pay the Defendant's cost of these proceedings, of Application No. 081/2010 and of the hearing on the standard basis to be assessed if not agreed.
Issued by
Ghada Audi
Acting Deputy Registrar
Date of Issue: 06 April 2011
At: 4pm