Case Information

Case numberCFI-014-2010
Citation number[2013] DIFC CFI 014
Case titleCFI 014/2010 - Order
Claimant (S)Taaleem PJSC
Defendant (S)Deyaar Development PJSC,National Bonds Corporation PJSC
Keywords--
Case reference--
Judges--
Judgement summary--

Judgement and Order

CFI 014/2010 - Order | DIFC Courts

Claim no: CFI 014/2012

 

THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS

 

IN THE COURT OF FIRST INSTANCE

 

BETWEEN

 

TAALEEM P.J.S.C.Claimant
and

 

NATIONAL BONDS CORPORATION P.J.S.C.

First Defendant
DEYAAR DEVELOPMENT P.J.S.C.Second Defendant

 

ORDER — AMLAK APPLICATION

 

UPON the First Defendant's application no. CFI 014/2010/19 against Amlak Finance P.J.S.C. and Amlak Sky Gardens LLC ("Amlak") for production of documents pursuant to RDC 28.32 having been struck out by Sir John Chadwick at a hearing on 15 January 2013 on the grounds that the DIFC Courts had no jurisdiction to hear it in the light of Decree No. (61) of 2009 as amended, which had transferred all petitions or claims relating to Amlak Finance P.J.S.C. to a Special Judicial Committee

 

AND UPON Sir John Chadwick's determination that the First Defendant should pay the Respondents, Amlak Finance P.J.S.C. and Amlak Sky Gardens LLC ("Amlak"), the costs of the application on a standard basis, and that costs would be assessed at a hearing if not agreed by 12 noon on 16 January 2013

 

AND UPON the Respondents' representative having notified the Registry via email dated 16 January 2013 that it had been agreed between the parties that the First Defendant would pay the Respondents costs in the sum of AED 72,500.00

 

IT IS ORDERED that:

 

The First Defendant pay the sum of AED 72,500.00 to Amlak as agreed.

 

Issued by:

Mark Beer

Registrar

Date of Issue: 5 February 2013