Rules and DecisionsJudgments & OrdersCFI 007/2011 - Application Order of HE Justice Ali Al Madhani

Case Information

Case numberCFI-007-2011
Citation number[2013] DIFC CFI 109
Case titleCFI 007/2011 - Application Order of HE Justice Ali Al Madhani
Claimant (S)Richard William Wheatley
Defendant (S)Simmons & Company International
Keywords--
Case reference--
Judges--
Judgement summary--

Judgement and Order

CFI 007/2011 - Application Order of HE Justice Ali Al Madhani | DIFC Courts

Claim No: CFI 007/2011

THE DUBAI INTERNATIONAL FINANCIAL CENTER COURTS

IN THE COURT OF FIRST INSTANCE

Between

RICHARD WILLIAM WHEATLEYClaimant

and

SIMMONS AND COMPANY INTERNATIONAL LIMITED

Defendant

ORDER OF H.E. JUSTICE ALI AL MADHANI

UPON reviewing the Claimant's application dated 27 May 2013 and the evidence attached to the application

AND UPON reviewing the Claimant's and Defendant's responses to the Claimant's application and the evidence attached to their responses

AND UPON reviewing the Claimant's reply to the Defendant's responses to the Claimant's application dated 23 June 2013

IT IS HEREBY ORDERED THAT:

1. The Claimant is entitled to costs of the action to be assessed if not agreed on the standard basis until 12 July 2012 (the date on which the relevant period expired) and on the indemnity basis thereafter, in addition to the assessment of all costs ordered as costs in the case.
2. The Claimant is entitled to the interest on those costs (to be inserted after the cost assessment) at a rate not exceeding the one month EIBOR +1% from 12 July 2012 (the date on which the relevant period expired) until the date of payment of the costs by the Defendant.
3. The detailed assessment of costs proceeding shall take place upon the conclusion of the case CA-001-2013 in the Court of Appeal.
4. The costs of this application are to be costs in this case.
5. Liberty to apply.

H.E. Justice Ali Al Madhani

Judge

Date of issue: 22 July 2013

At: 3pm