Judgement and Order
Claim No. CFI-014-2018
THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS
IN THE COURT OF FIRST INSTANCE
BETWEEN
NATIONAL CONTRACTING CO. LTD.
and
DODSAL ENGINEERING & CONSTRUCTION PTE. LIMITED
ORDER OF JUDICIAL OFFICER NASSIR AL NASSER
UPON the request made by the Claimant on 23 April 2018 for a Default Judgment (the “Request”) in accordance with Rule 13.1 (1) and (2) of the Rules of the DIFC Courts (“RDC”), it is found as follows:
1.The Request is one prohibited by RDC 13.3 (1) and (2).
2. The Defendant has filed an Acknowledgment of Service on 2 April 2018 and a Defence to the claim on 24 April 2018.
ACCORDINGLY IT IS HEREBY ORDERED THAT:
3. The Request is denied.
4. The Claimant shall bear the cost of this application.
Issued by:
Ayesha Bin Kalban
Assistant Registrar
Date of Issue: 15 May 2018