Rules and DecisionsJudgments & OrdersCFI 082/2018 McConnell Dowell South East Asia Pte Limited v Essar Projects Limited

Case Information

Case numberCFI-082-2018
Citation number[2019] DIFC CFI 071
Case titleCFI 082/2018 McConnell Dowell South East Asia Pte Limited v Essar Projects Limited
Claimant (S)McConnell Dowell South East Asia Pte Limited
Defendant (S)Essar Projects Limited
Keywords--
Case reference--
Judges--
Judgement summary--

Judgement and Order

CFI 082/2018 McConnell Dowell South East Asia Pte Limited v Essar Projects Limited | DIFC Courts

Claim No: CFI-082-2018

THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS

 

IN THE COURT OF FIRST INSTANCE

BEFORE JUDICIAL OFFICER NASSIR AL NASSER

 

BETWEEN

 

McCONNELL DOWELL SOUTH EAST ASIA PTE LIMITED

Claimant/Applicant

and

ESSAR PROJECTS LIMITED

Defendant/Respondent


ORDER OF JUDICIAL OFFICER NASSIR AL NASSER


UPON reviewing the Defendant’s Application Notice CFI-082-2018/3 for a Court Order to stay proceedings pending the decision of the Joint Judicial Committee;

AND UPON reviewing the evidence provided;

IT IS HEREBY ORDERED THAT:

1.The above mentioned proceedings before this Court, including any and all outstanding applications, appeals and procedures, be stayed pending the final determination by the JJC.

2. There shall be no order as to costs.

 

Issued by:

Ayesha Bin Kalban

Assistant Registrar

Date of issue: 1 May 2019