Case Information
| Case number | CFI-070-2018 |
| Citation number | [2021] DIFC CFI 174 |
| Case title | CFI 070/2018 IBDI Bank Limited V (1) Mabani Delma General Contracting Co LLC (2) Heliopolis Electric Company LLC (3) Delma Engineering Projects Company LLC (4) Delma Emirates Diesel (5) Delma Emirates... |
| Claimant (S) | IBDI Bank Limited |
| Defendant (S) | (1) Mabani Delma General Contracting Co LLC (2) Heliopolis Electric Company LLC (3) Delma Engineering Projects Company LLC (4) Delma Emirates Diesel (5) Delma Emirates... |
| Keywords | -- |
| Case reference | -- |
| Judges | -- |
| Judgement summary | -- |
Judgement and Order
Claim No: CFI 070/2018
THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS
IN THE COURT OF FIRST INSTANCE
BETWEEN
IBDI BANK LIMITED
Claimant
and
(1) MABANI DELMA GENERAL CONTRACTING CO LLC
(2) HELIOPOLIS ELECTRIC COMPANY LLC
(3) DELMA ENGINEERING PROJECTS COMPANY LLC
(4) DELMA EMIRATES DIESEL
(5) DELMA EMIRATES GENERAL TRANSPORT
(6) AHMED KHALIL KHALED ALMERAIKHI
(7) SHERIFA AHMED KHALIL KHALED ALMERAIKHI
(8) MARIAM AHMED KHALED ALMERAIKHI
Defendants
ORDER OF DISCONTIUANCE OF THE CLAIM AGAINST THE SECOND DEFENDANT
UPON the Claimant’s Application dated 19 April 2021 seeking an Order of Discontinuance against the Second Defendant only.
UPON the agreement of the parties that the claim against the Second Defendant be discontinued
AND UPON noting that the Claimant reserves the right to reinstate the claim against the Second Defendant
IT IS HEREBY ORDERED THAT:
1. The claim be discontinued as against the Second Defendant only.
2. The proceedings shall continue as against all other Defendants.
3. The Claimant shall pay the Second Defendant’s legal fees in the agreed amount of AED 20,000 in full and final settlement of all costs in respect of the present proceedings.
Issued by:
Ayesha Bin Kalban
Deputy Registrar
Date of issue: 16 May 2021
Time: 2pm