Case Information

Case numberCFI-070-2018
Citation number[2021] DIFC CFI 373
Case titleCFI 070/2018 Idbi Bank Limited v (1) Mabani Delma General Contracting Co LLC (2) Delma Engineering Projects Company LLC (3) Delma Emirates Diesel (4) Delma Emirates General Transport (5) Ahmed Khalil...
Claimant (S)IDBI Bank Limited
Defendant (S)Ahmed Khalil Khaled Almeraikhi,Delma Emirates Diesel,Delma Emirates General Transport,Delma Engineering Projects Company LLC,Heliopolis Electric Company LLC,Mabani Delma General Contracting Co LLC,Mariam Ahmed Khaled Almeraikhi,Sherifa Ahmed Khalil Khaled Almeraikhi
Keywords--
Case reference--
Judges--
Judgement summary--

Judgement and Order

CFI 070/2018 Idbi Bank Limited v (1) Mabani Delma General Contracting Co LLC (2) Delma Engineering Projects Company LLC (3) Delma Emirates Diesel (4) Delma Emirates General Transport (5) Ahmed Khalil Khaled Almeraikhi (6) Sherifa Ahmed Khalil Khaled Almeraikhi (7) Mariam Ahmed Khaled Almeraikhi | DIFC Courts

Claim No. CFI 070/2018

THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS

IN THE COURT OF FIRST INSTANCE

BETWEEN

IDBI BANK LIMITED

Claimant

and

(1) MABANI DELMA GENERAL CONTRACTING CO LLC
(2) DELMA ENGINEERING PROJECTS COMPANY LLC
(3) DELMA EMIRATES DIESEL
(4) DELMA EMIRATES GENERAL TRANSPORT
(5) AHMED KHALIL KHALED ALMERAIKHI
(6) SHERIFA AHMED KHALIL KHALED ALMERAIKHI
(7) MARIAM AHMED KHALED ALMERAIKHI

Defendants


CONSENT ORDER


UPON the Agreed Amended Case Management Order dated 10 June 2021 (the “CMC Order”)

AND UPON the Claimant and the Defendants having agreed to vary the terms of the CMC Order as set out below

IT IS HEREBY ORDERED BY CONSENT:

1. Paragraph 10 of the CMC Order shall be varied to provide that:

“Signed statements of witnesses of fact, and hearsay notices where required, shall be served following the close of the disclosure stage, and in any event by 4pm on 14 November 2021.”

2. Paragraph 11 of the CMC Order shall be varied to provide that:

“Supplementary statements of witnesses of fact shall be served by 4pm on 28 November 2021.”

3. Paragraph 14 of the CMC Order shall be varied to provide that:

“Expert Reports, if any, shall be filed and served by 4pm on 5 December 2021.”

4. Paragraph 15 of the CMC Order shall be varied to provide that:

“Supplemental Expert Reports, if any, shall be filed and served by 4pm on 19 December 2021.”

5. The remainder of the CMC Order shall except as provided above, remain unchanged.

Issued by:
Nour Hineidi
Registrar
Date of Issue: 19 October 2021
At: 8am