Rules and DecisionsJudgments & OrdersCFI 054/2018 SBM Bank (Mauritius) Ltd v (1) Renish Petrochem FZE (2) Mr Hiteshkumar Chinubhai Mehta (3) Prime Energy FZE (4) National Bank Of Kuwait S.A.K.P

Case Information

Case numberCFI-054-2018
Citation number[2022] DIFC CFI 186
Case titleCFI 054/2018 SBM Bank (Mauritius) Ltd v (1) Renish Petrochem FZE (2) Mr Hiteshkumar Chinubhai Mehta (3) Prime Energy FZE (4) National Bank Of Kuwait S.A.K.P
Claimant (S)SBM Bank (Mauritius) Ltd
Defendant (S)(1) Renish Petrochem FZE (2) Mr Hiteshkumar Chinubhai Mehta (3) Prime Energy FZE (4) National Bank Of Kuwait S.A.K.P
Keywords--
Case reference--
Judges--
Judgement summary--

Judgement and Order

CFI 054/2018 SBM Bank (Mauritius) Ltd v (1) Renish Petrochem FZE (2) Mr Hiteshkumar Chinubhai Mehta (3) Prime Energy FZE (4) National Bank Of Kuwait S.A.K.P | DIFC Courts

Claim No. CFI 054/2018

THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS

IN THE COURT OF FIRST INSTANCE

BETWEEN

SBM BANK (MAURITIUS) LTD

Claimant

and

(1) RENISH PETROCHEM FZE
(2) MR HITESHKUMAR CHINUBHAI MEHTA
(3) PRIME ENERGY FZE
(4) NATIONAL BANK OF KUWAIT S.A.K.P

Defendants


CONSENT ORDER


UPON the Defendants' renewed application filed on 3 June 2022 for permission to appeal pursuant to RDC 44.9 (" Renewed PTA Application")

AND UPON the Claimant having filed written submissions in response to the Renewed PTA Application on 22 June 2022

AND UPON the Claimant and Defendants having agreed to the terms of this Consent Order

BY CONSENT IT IS ORDERED THAT:

1. The Renewed PTA Application shall be determined by the Court of Appeal on the papers, without the need for an oral hearing.

2. No order as to costs.

Issued by:
Nour Hineidi
Registrar
Date of Issue: 28 June 2022
At: 12pm