Claim No. CFI-001-2012

THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS
IN THE COURT OF FIRST INSTANCE
BEFORE H.E. JUSTICE OMAR AL MUHAIRI
BETWEEN

YAHYA AL SHAYKH Claimant
andDUBAI INTERNATIONAL FINANCIAL CENTRE AUTHORITY Defendant

PRE-TRIAL REVIEW ORDER OF H.E. JUSTICE OMAR AL MUHAIRI

UPON reviewing the relevant documents in the Court file;

AND UPON hearing the Claimant in person and the Defendant’s counsel at the Pre-Trial Review hearing held on 12 September 2012;

IT IS HEREBY ORDERED THAT:

Trial Timetable

1. The Trial timetable be set as follows:

10 am Claimant’s opening submissions
10:30 am Defendant’s opening submissions
11 am Witness evidence of Mr Hani Hirzallah
12 noon Lunch Break
2pm Claimant’s closing submissions
2:30pm Defendant’s closing submissions

 

Trial Bundles

2. Further to item 13 of the CMC Order dated 13 June 2012 (the “CMC Order“), the Defendant will liaise with the Claimant to prepare trial bundles. Trial bundles to be lodged with the Court by 30 September 2012.

 

Skeleton Arguments

3. Paragraph 15 of the CMC Order be amended such that:

(a) the Claimant to file and serve his Skeleton Argument and any written Opening Statements by 4pm on Thursday, 11 October 2012;
(b) the Defendant to file and serve its Skeleton Argument and any written Opening Statements by 4pm on Monday, 15 October 2012.

 

Chronology

4. Paragraph 16 of the CMC Order be amended such that the parties prepare separate chronologies of significant events to be filed and served by 4pm on Thursday, 11 October 2012.

 

Trial Date

5. The trial in this matter is confirmed to take place at 10am on 18 October 2012.

 

Costs of the Pre-Trial Review

6. Costs in the case.

 

Issued by

Mark Beer
Registrar
Date: 13 September 2012
At: 5pm

X

Privacy Policy

The Dispute Resolution Authority and all its affiliates are committed to preserve the confidentiality, integrity and availability of client data and personal information.

Dispute Resolution Authority and all its affiliates employees, vendors, contract workers, shall follow Information Security Management System in all the processes and technology.

  1. DRA's Top Management is committed to secure information of all our interested parties.
  2. Information security controls the policies, processes, and measures that are implemented by DRA in order to mitigate risks to an acceptable level, and to maximize opportunities in order to achieve its information security objectives.
  3. DRA and all its affiliates shall adopt a systematic approach to risk assessment and risk treatment.
  4. DRA is committed to provide information security awareness among team members and evaluate the competency of all its employees.
  5. DRA and all its affiliates shall protect personal information held by them in all its form.
  6. DRA and all its affiliates shall comply with all regulatory, legal and contractual requirements.
  7. DRA and all its affiliates shall provide a comprehensive Business Continuity Plan encompassing the locations within the scope of the ISMS.
  8. Information shall be made available to authorised persons as and when required.
  9. DRA’s Top Management is committed towards continual improvement in information security in all our processes through regular review of our information security management system.