Claim no: CFI 014/2012

 

THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS

 

IN THE COURT OF FIRST INSTANCE

 

BETWEEN

 

TAALEEM P.J.S.C. Claimant
and
 
NATIONAL BONDS CORPORATION P.J.S.C.
First Defendant
DEYAAR DEVELOPMENT P.J.S.C. Second Defendant

 

ORDER — AMLAK APPLICATION

 

UPON the First Defendant’s application no. CFI 014/2010/19 against Amlak Finance P.J.S.C. and Amlak Sky Gardens LLC (“Amlak”) for production of documents pursuant to RDC 28.32 having been struck out by Sir John Chadwick at a hearing on 15 January 2013 on the grounds that the DIFC Courts had no jurisdiction to hear it in the light of Decree No. (61) of 2009 as amended, which had transferred all petitions or claims relating to Amlak Finance P.J.S.C. to a Special Judicial Committee

 

AND UPON Sir John Chadwick’s determination that the First Defendant should pay the Respondents, Amlak Finance P.J.S.C. and Amlak Sky Gardens LLC (“Amlak”), the costs of the application on a standard basis, and that costs would be assessed at a hearing if not agreed by 12 noon on 16 January 2013

 

AND UPON the Respondents’ representative having notified the Registry via email dated 16 January 2013 that it had been agreed between the parties that the First Defendant would pay the Respondents costs in the sum of AED 72,500.00

 

IT IS ORDERED that:

 

The First Defendant pay the sum of AED 72,500.00 to Amlak as agreed.

 
Issued by:
Mark Beer
Registrar
Date of Issue: 5 February 2013
At: 11am

X

Privacy Policy

The Dispute Resolution Authority and all its affiliates are committed to preserve the confidentiality, integrity and availability of client data and personal information.

Dispute Resolution Authority and all its affiliates employees, vendors, contract workers, shall follow Information Security Management System in all the processes and technology.

  1. DRA's Top Management is committed to secure information of all our interested parties.
  2. Information security controls the policies, processes, and measures that are implemented by DRA in order to mitigate risks to an acceptable level, and to maximize opportunities in order to achieve its information security objectives.
  3. DRA and all its affiliates shall adopt a systematic approach to risk assessment and risk treatment.
  4. DRA is committed to provide information security awareness among team members and evaluate the competency of all its employees.
  5. DRA and all its affiliates shall protect personal information held by them in all its form.
  6. DRA and all its affiliates shall comply with all regulatory, legal and contractual requirements.
  7. DRA and all its affiliates shall provide a comprehensive Business Continuity Plan encompassing the locations within the scope of the ISMS.
  8. Information shall be made available to authorised persons as and when required.
  9. DRA’s Top Management is committed towards continual improvement in information security in all our processes through regular review of our information security management system.