Claim No: CA-004-2016

THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS

IN THE COURT OF FIRST INSTANCE

BETWEEN

DEYAAR DEVELOPMENT PJSC

                                                                          Appellant/Judgment Debtor

and

NATIONAL BONDS CORPORATION PJSC

Respondent/Judgment Creditor


  ORDER


UPON considering the Appellant’s Grounds of Appeal and Skeleton Argument dated 15 March 2016

AND UPON reading the Enforcement Order of the Registrar dated 18 August 2015 pursuant to (discontinued) enforcement proceedings ENF-030-2015

AND UPON reading the Order of H.E. Justice Omar Al Muhairi dated 3 March 2016

AND UPON hearing Counsel for the Appellant on 25 May 2016

AND UPON reviewing the documents recorded on the Court file

IT IS HEREBY ORDERED THAT:

1.The Appellant’s appeal is allowed.

2. Paragraph 4 of the Enforcement Order made by the Registrar dated 18 August 2015 be set aside.

3. The sum of AED 7,449,804.47 deposited by the Appellant into Court pursuant to the Order of the Chief Justice Michael Hwang dated 10 April 2016 be refunded by the DIFC Courts to the Appellant.

4. There be no order as to costs.

 

Issued by:

Natasha Bakirci

Assistant Registrar

Date of Issue: 2 June 2016

At: 3pm

REASONS:

1.The Order of the Registrar dated 18 August 2015 was an Interim Enforcement Order (the “Interim Order”) made following two judgments of Justice Sir David Steel dated 19 February 2014 and 23 March 2014 in CFI-014-2010 by which the Appellant was ordered to pay the respondent AED 227,379,430.68 and to pay the costs of the Claimant in CFI-014-2010 and of the Respondent to this appeal.

2. By paragraph 1 of the Interim Order a charge was imposed on the Appellant’s interest in the Units in Sky Gardens and by paragraph 4 thereof the Appellant was ordered pursuant to Part VI(a) Schedule 1 to Practice Direction No. 4 of 2015 to pay an amount equal to 3% of the value of the unpaid Judgments and Orders in the sum of AED 7,449,804.47.

3. Before a hearing to determine whether a final charging order should be made, the Respondent filed a notice of discontinuance of its enforcement claim and consequently the interim charging order was never converted to a final order.

4. Part VI(a) of Schedule 1 to PD No. 4 of 2015 provides:

“(i) no fee will be payable by the party filing for enforcement.

(ii) 3% of the value of the judgment or order is to be settled by the party against whom enforcement has been filed.”

5. An application by the Appellant to set aside paragraph 4 of the Interim Order was dismissed by H.E. Justice Omar Al Muhairi who held inter alia that Part VI(a) of Schedule 1 to PD No. 4 of 2015 did not require that the relevant enforcement proceedings had been concluded by the making of a final order or discharging the interim order.

6. In the view of the DIFC Court of Appeal, Part VI(a) of Schedule 1 to PD No. 4 of 2015 should be given a purposive construction and, so construed, the enforcement fee only becomes payable after a final enforcement order is made.

7. Since no final enforcement order was made in this case, it follows that the Appellant’s appeal succeeds and paragraph 4 of the Interim Order should be set aside.

X

Privacy Policy

The Dispute Resolution Authority and all its affiliates are committed to preserve the confidentiality, integrity and availability of client data and personal information.

Dispute Resolution Authority and all its affiliates employees, vendors, contract workers, shall follow Information Security Management System in all the processes and technology.

  1. DRA's Top Management is committed to secure information of all our interested parties.
  2. Information security controls the policies, processes, and measures that are implemented by DRA in order to mitigate risks to an acceptable level, and to maximize opportunities in order to achieve its information security objectives.
  3. DRA and all its affiliates shall adopt a systematic approach to risk assessment and risk treatment.
  4. DRA is committed to provide information security awareness among team members and evaluate the competency of all its employees.
  5. DRA and all its affiliates shall protect personal information held by them in all its form.
  6. DRA and all its affiliates shall comply with all regulatory, legal and contractual requirements.
  7. DRA and all its affiliates shall provide a comprehensive Business Continuity Plan encompassing the locations within the scope of the ISMS.
  8. Information shall be made available to authorised persons as and when required.
  9. DRA’s Top Management is committed towards continual improvement in information security in all our processes through regular review of our information security management system.