Claim No: CFI 007/2011
THE DUBAI INTERNATIONAL FINANCIAL CENTER COURTS
IN THE COURT OF FIRST INSTANCE
Between
RICHARD WILLIAM WHEATLEY | Claimant |
and SIMMONS AND COMPANY INTERNATIONAL LIMITED | Defendant |
ORDER OF H.E. JUSTICE ALI AL MADHANI
UPON reviewing the Claimant's application dated 27 May 2013 and the evidence attached to the application
AND UPON reviewing the Claimant's and Defendant's responses to the Claimant's application and the evidence attached to their responses
AND UPON reviewing the Claimant's reply to the Defendant's responses to the Claimant's application dated 23 June 2013
IT IS HEREBY ORDERED THAT:
1. The Claimant is entitled to costs of the action to be assessed if not agreed on the standard basis until 12 July 2012 (the date on which the relevant period expired) and on the indemnity basis thereafter, in addition to the assessment of all costs ordered as costs in the case.
2. The Claimant is entitled to the interest on those costs (to be inserted after the cost assessment) at a rate not exceeding the one month EIBOR +1% from 12 July 2012 (the date on which the relevant period expired) until the date of payment of the costs by the Defendant.
3. The detailed assessment of costs proceeding shall take place upon the conclusion of the case CA-001-2013 in the
Court of Appeal.
4. The costs of this application are to be costs in this case.
5. Liberty to apply.
H.E. Justice Ali Al Madhani
Judge
Date of issue: 22 July 2013
At: 3pm