June 03, 2026 court of first instance - Orders
Claim No: CFI 053/2024
THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS
In the name of His Highness Sheikh Mohammad Bin Rashid Al Maktoum, Ruler of Dubai
IN THE COURT OF FIRST INSTANCE
BETWEEN
QATAR GENERAL INSURANCE & REINSURANCE COMPANY QSPC
Claimant
and
EMRGENT RISK SOLUTIONS LIMITED
Defendant
| Hearing : | 26 – 29 January 202 |
|---|---|
| Counsel : | Mr David Walsh KC instructed by Holman Fenwick Willan Middle East LLP for the Claimant Mr Guy Blackwoord KC, instructed by Wordley Partnership for the Defendant |
| Judgment : | 3 June 2026 |
JUDGMENT OF H.E. JUSTICE SAPNA JHANGIANI
UPON the Part 7 Claim Form dated 25 July 2024 (the “Claim”)
AND UPON the amended versions of DIFC Law No. 6 of 2004 (the “Contract law”); DIFC Law No. 5 of 2005 (the “Law of Obligations”); DIFC Law No. 6 of 2005 (the “Implied Terms Law”); and DIFC Law. No 7 of 2005 (the “Law of Damages and Remedies”)
AND UPON hearing Counsel for the Claimant and Counsel for the Defendant at the trial before H.E. Justice Sapna Jhangiani from 26 to 29 January 2026 (the “Trial”)
AND PURSUANT TO the Rules of the DIFC Courts (“RDC”)
IT IS HEREBY ORDERED THAT:
1. The Defendant has breached its obligations to the Claimant under the Contract (as defined below) and is liable for damages as a result thereof.
2. The Defendant is to pay to the Claimant the amount of QAR 6,089,712.00 in respect of HOC1 (as defined below) by way of damages for breach of contract.
3. The Defendant is to pay to the Claimant the amount of QAR 146,724.61 in respect of HOC2 (as defined below) by way of damages for breach of contract. Sums due from the Defendant to the Claimant in respect of HOC2 continue to accrue.
4. If the Claimant pays an invoice in respect of HOC2 or HOC3 (as defined below), it will be entitled to be indemnified by the Defendant for the Defendant’s half share of that invoice, by way of damages for the Defendant’s breach of contract, if either:
(a) Liberty Specialty Markets (Lloyd’s Syndicate LIB 4472) has paid or agreed to pay that invoice; or
(b) The Claimant presents the necessary documents and information in support of its right to an indemnity under Article 790 of the Qatar Civil Code.
5. If there is any dispute about the entitlement of the Claimant under subparagraphs 4(a) or 4(b) above, the parties may return to Court to have the matter determined.
6. Compound interest shall apply to the sum of QAR 6,089,712.00 ordered to be paid to the Claimant by the Defendant at paragraph 2 above at a rate of 9% from 7 December 2020.
7. Within 14 days of today’s date, the Claimant shall file costs submissions, and is invited to file further submissions on the date from which interest should run for the Defendant’s half share of each of the four payments made by the Claimant so far in respect of HOC2.
8. The Defendant shall file reply submissions within 14 days of the Claimant’s submissions referred to at paragraph 7 above.
Issued by:
Delvin Sumo
Assistant Registrar
Date of issue: 3 June 2026
At: 11am
SCHEDULE OF REASONS
A. BACKGROUND
1. The Claimant is an insurance and reinsurance company incorporated in Qatar. The Defendant is in business as a reinsurance and retrocession broker. This dispute arises from a contract between the Claimant and the Defendant (the “Contract”) by which the Defendant agreed to place retrocession coverage for reinsurance cover provided by the Claimant (the “Reinsurance”).
The Underlying Insurance
2. The underlying insurance (“Underlying Insurance”) comprised excess liability insurance underwritten by Doha Insurance Group QPSC (“Doha”). The Underlying Insurance was provided in respect of the Nakilat Damen Shipyard in Qatar (the “Shipyard”), which contained a superyacht facility (the “Superyacht Facility”).
3. The Superyacht Facility was owned by Qatar Petroleum (“QP”) (now Qatar Energy) which granted a licence to Qatar Gas Transport Company Ltd (“Nakilat”) to access, occupy and use certain areas within the Shipyard, including the Superyacht Facility. The licence was granted under an “Access and Indemnification Agreement” dated 1 June 2011 (and amended on 1 March 2014). Nakilat Damen Shipyards Qatar (“NDSQ”, a JV of Nakilat and Damen Shipyards Qatar Holding BV) was a “Permitted Sublicensee” under the Access and Indemnification Agreement, and was licensed to conduct, amongst other things, superyacht repairs in the Shipyard.
4. The Underlying Insurance was issued to the following co-assureds (the “Underlying Insureds”), together with their contractors, subcontractors and consultants to the extent performing work for NDSQ, as well as their officers, directors and employees etc.:
(a) Nakilat;
(b) NDSQ;
(c) Nakilat-Keppel Offshore & Marine;
(d) Damen Shipyards Qatar Holding BV;
(e) KS Investments Pte Ltd;
(f) QP (now Qatar Energy or “QE”).
5. The Underlying Insureds entered into the Underlying Insurance on around 1 June 2018. The Underlying Insurance was valid from 1 June 2018 to 31 May 2020 and, among other terms, was governed by the laws of Qatar and subject to the exclusive jurisdiction of the Courts of Qatar. It contained three sections of cover:
(a) Section 1: Ship repairer’s Legal Liabilities – this insurance was primarily written on the standard-form London Ship Repairers Liability Clauses wording LSW169A, with certain amendments;
(b) Section 2: General Third Party Liabilities – this incorporated standard-form Excess Liability Claims Made Policy LSW 244 and expressly included “cover for NDSQ’s potential liabilities in respect of Qatar Petroleum’s property and, in particular, property leased, occupied or in the care, custody and control of NDSQ”, which would include the Superyacht Facility; and
(c) Section 3: Excess liabilities, with wording from Excess Liability Claims Made Policy LSW 244.
6. The specific policy wording under Sections 1 and 2 of the Underlying Insurance is relevant to the dispute between the parties and is addressed further below.
The Reinsurance
7. Doha elected to reinsure its exposure with three different markets: one brokered by AON to the extent of 40% of the risk assumed (the “AON Reinsurance”); the Reinsurance with the Claimant to the extent of 10% of Doha’s risk; and the remaining 50% of the risk was placed with other reinsurers. On the face of it, Doha Insurance did not retain any of the risk itself.
8. The Claimant entered into the Reinsurance with Doha for a 10% share of 100% of the Underlying Insurance by a contract of reinsurance entered into on or about 16 July 2018. The Reinsurance contained the same clauses as the Underlying Insurance, and was also governed by Qatar law and subject to the exclusive jurisdiction of the Courts of Qatar.
9. Under the AON Reinsurance (bearing Policy Number MALIA1800254):
(a) QBE (Lloyd’s Syndicate COF 1036) (“QBE”) signed for 16% of the 40%; and
(b) Liberty Specialty Markets (Lloyd’s Syndicate LIB 4472) (“Liberty”) signed for 14% of the 40%, and a further 3.29% of the 40% by virtue of its participation in another syndicate.
10. In the AON slip (the “AON Slip”), “QBE Syndicate 1036” (i.e. QBE) were designated as ‘Slip Leader’. The AON Slip is also subject to Qatar law and the jurisdiction of the Qatari courts.
11. The AON Reinsurance was governed by materially the same clauses as the Underlying Insurance, save for one exception argued for by the Defendant. The Defendant contends that a general cross-liability clause (providing coverage for claims between the Underlying Insureds) was excluded under Section 1 of the Underlying Insurance, but wrongly referred to in the AON Slip as being included under Section 1. This is addressed further below.
The Contract and Retrocession Coverage
12. The Claimant and the Defendant entered into the Contract on or around 18 July 2018. By the Contract, the Defendant agreed to place retrocession coverage for the Reinsurance.
13. It is not disputed that the Contract:
(a) is governed by the law of the DIFC;
(b) is a contract of agency within the meaning of Article 124 of the DIFC Contract Law.
14. On 15 July 2018, Mr Alterhi of the Claimant emailed Mr Reichardt of the Defendant, attaching the 2-year Reinsurance in respect of which the Defendant was instructed to seek retrocession. The Claimant offered a 10% share with total deduction of 20% to the Defendant. The AON Slip was forwarded by Mr Alterhi to Mr Reichardt and Mr Tommy of the Defendant on 17 July 2018.
15. On 18 July 2018, Mr Tommy of the Defendant confirmed that MS Amlin Lloyd’s Syndicate No. 2001 (“Amlin”) had offered a 5% line and asked Mr Alterhi to confirm whether the Defendant could proceed to bind them, and also to confirm that the slip and premium were to mirror the AON Slip led by QBE in London. Mr Alterhi provided his confirmation by response of the same day.
16. The Amlin slip (“Amlin Slip”) provides that the “Lead Reinsurer” is “Syndicate 1036 managed by QBE at Lloyds of London” even though QBE do not underwrite any of the risk under the Amlin slip. The Amlin Slip is scratched (i.e. has a manuscript annotation) which provides “RE Reference at 2019. Renewal if required”. Nothing appears to turn on this.
17. On 18 July 2018, the Defendant contacted Lochain Patrick Insurance Brokers (“LPIB”) for the purpose of placing the final half (5%) of the Claimant’s share of risk under the Reinsurance.
18. On 23 July 2018, Mr Tommy of the Defendant confirmed to Mr Alterhi of the Claimant that there was support from “Liberty” (ie. Liberty Speciality Markets Lloyd’s Syndicate No. 4472) for writing the balance 5% retrocession, on the terms of the AON Slip. Mr Alterhi asked Mr Tommy on 24 July to bind Liberty, and the Defendant in turn confirmed this to LPIB.
19. The Liberty slip with reference B06111MR1812138 (the “Liberty Slip”) was sent to Mr Tommy of the Defendant by LPIB on 27 July 2018 and included the following “Notice of Cancellation Clause” which was “scratched” (i.e. written by hand):

20. The same manuscript wording was included in the “Risk Details” section of the Liberty Slip:

21. I shall refer to the Notices referred to at paragraphs 19 and 20 above collectively as the “Cancellation Notice”.
22. The Liberty Slip was again sent by LPIB to the Defendant on 14 August 2018 as part of the “formal documentation for your file”.
23. On 28 October 2018, Mr Alterhi of the Claimant queried in an email to Mr Tommy of the Defendant the amount of premium being charged on the account. In reply, Mr Tommy confirmed that the coverage was for 2 years and explained that the reason for the tax invoice showing a single-year period was due to the Defendant’s internal IT systems:
“I…would like to clarify that the RI slip is for a 2 year period starting 31st May 2018 and ending 31st May 2020, the Minimum and Deposit Premium specified in the slip is ANNUAL, therefore, for a 2 year period, the premium is USD 501,000 * 2 = USD 1,002,000.
Our Tax Invoice raised however shows the period as 1st June 2018 to 31st May 2019, which came by DEFAULT under the IT system, you may kindly ignore the period in our debit note. The correct premium is mentioned in both the slip as well as our closings. Hope the above clarifies the issue raised by you, but do let me know if you need to discuss for better clarity.”
24. On 30 October 2018, Mr Reichardt of the Defendant asked Mr Alterhi to confirm that 100% of the premium would be paid in two equal annual instalments, and asked for confirmation of the annual instalment dates.
25. The Defendant’s helpful diagram of the insurance scheme referred to in these proceedings (with the Claimant referred to as “QGIRC” and the Defendant referred to as “ARB Re”, reflecting its previous name “Arab European Reinsurance Brokers Ltd”), is as follows:

26. The “claims control clauses” in the AON Reinsurance referred to in the above diagram are in relevant part as follows:
“Claims Control Clause
The Reassured hereby undertakes to give immediate notice to Underwriters of any occurrence which may give rise to a claim hereunder as soon as they themselves are aware of same and in such event the Underwriters hereon will take over all responsibility for handling such claim and will provide the Reassured with all instructions which shall be followed by the Reassured at all times, including the settlement of such claim. In no case will the reassured make any admission of liability or payment under the original policy without the consent of the Underwriters hereon having been obtained”…
BASIS OF CLAIMS AGREEMENT Claims to be managed in accordance with: - The Lloyd’s Claim Scheme (Combined) or as amended or any successor thereto. The applicable Scheme/part will be determined by the rules and scope of the Scheme(s); - IUA claims agreement practices; - The practices of any (re)insurer(s) electing to agree claims in respect of their own participation. Unless otherwise detailed in the Risk Details, the Slip Leader may instruct any third party expert to investigate and adjust any claim or circumstance notified to the contract….
CLAIMS AGREEMENT PARTIES The Lead Claims Agreement Party is deemed to be the Slip Leader unless otherwise specified here.
For Lloyd’s syndicates, the leading Lloyd’s syndicate and, where required by the applicable Lloyd’s Claims Scheme, the second Lloyd’s syndicate. The second Lloyd’s syndicate is N/A.
For company (re)insurers, all IUA subscribing companies agree to follow the IUA claims agreement practices. All other subscribing (re)insurers… agree to follow the decisions of the Lloyd’s and IUA claims agreement parties or the lead Claims Agreement Party…”
The Loss and Insurance Claims
27. On Sunday 11 August 2019, a fire in Super Yacht Hall 11 (the “Superyacht Hall”) caused the total loss of three yachts housed inside the hall at the time, as well as damage to the Superyacht Hall itself (the “Loss”). (There are references in the record to both Halls 10 and 11 being damaged, but nothing appears to turn on this, and I shall refer to “Superyacht Hall” in the singular).
28. Following the Loss, the following heads of claim have been made against the Underlying Insurance:
(a) Head of Claim 1 (“HOC1”) relating to damage to the yachts stored in the Superyacht Hall. The yachts were deemed to be constructive total losses. The claim was settled pursuant to a settlement agreement dated 21 August 2020 between the owners of the yachts, represented by Amiri Yachts Authority, Nakilat, NDSQ, and Doha (the “Yachts Settlement Agreement”). The total amount of the settlement was USD 33,368,285.00, comprising a USD 30 million settlement amount as well as a call on a performance guarantee provided by NDSQ in the sum of USD 3,368,285.
(b) Head of Claim 2 (“HOC2”) comprising a claim by Qatar Energy against NDSQ and Nakilat relating to the costs of dismantling and removing the damaged superyachts, along with other costs and expenses incurred in connection with the claim. The current total of this sum is approximately USD 806,179.17.
(c) Head of Claim 3 (“HOC3”) is an unrepaired damage claim for damages to the Superyacht Hall itself. At present, no claims have formally been presented under HOC3, but it is anticipated that claims will be presented in due course.
29. On 1 September 2019, Mr Reichardt of the Defendant sent the following email to Mr Retheeshkumar Rajappan of the Claimant:
“Further to my claim acknowledgement mail sent to you on 28th August, we have just learnt from the market that the Lead Reinsurer on this risk have sent a notice of cancellation in the Year 1 and they are renegotiating the terms for Year 2 renewal. Can you please investigate this with the Lead Co-Insurer and advise if final terms were duly agreed with the Leader, if so, please convey these for our records and conveying to the Reinsurers that subscribed to the 10% order that you placed with us. In case the terms for Year 2 are still not concluded, then the claim notified by you may not be admissible as there would be no cover in place then.”
30. On 5 September 2019, Mr Tommy of the Defendant sent the Cancellation Notice to the Claimant, attached to the following email to Mr Alterhi:
“Further to the telephone conversation that you had with Ben this morning, when you wanted to know as to when the provisional notice of cancellation (PNOC) was served by the Underwriter, I am sending to you the slip signed by Liberty through our sub-broker Lochain & Patrick, which was sent to you in evidence of the 5% Line that we placed with Liberty. Liberty has also taken a larger Line from the Main Co-Insurer of Nakilat. You will see from the pages 1 and 37 of the stamped slip, that provisional notice of cancellation was deemed to be given on the date that they signed the slip.”
31. On 21 November 2019, Mr Alterhi wrote to Mr Tommy in the following terms:
“With regards to the cover note issued, as a professional broker you didn’t alert us about “notice deemed to be cancelled from inception”, which is NOT AS PER THE ORIGINAL AON SLIP forwarded to you and after your confirmation that Liberty accepted the risk as PER AONS TERMS via your email dated 23.07.2018 and although that period is for two years from 31.05.2018 to 31.05.2020.
After commencing of the second year from 31.05.2019, you failed to inform us that Liberty is no longer on risk.”
32. On 23 November 2019, Mr Alterhi requested that Mr Tommy: “Please forward the email you sent that shows Liberty’s slip [containing the Cancellation Notice] at inception”. The same request was made again by Mr Alterhi on 4 December 2019. There are no documents on the record evidencing that the Liberty Slip was sent to the Claimant prior to 5 September 2019.
33. Liberty has taken the position that it is not liable to indemnify the Claimant for the Loss on the basis that there was no retrocession cover in place under the Liberty Slip during the period of the Loss on account of the Cancellation Notice.
34. The Claimant brings the current claim against the Defendant, arguing that the Defendant breached its duty of care to the Claimant (both in tort and contract) by failing to procure back-to-back retrocession cover for the Claimant, and failing to inform the Claimant of Liberty’s Cancellation Notice prior to the expiry of Liberty’s retrocession cover (the “Liberty Retrocession Cover”). The Claimant contends that but for the Defendant’s breaches, it would have been indemnified by Liberty. It claims against the Defendant for the current and future amounts it contends Liberty would have been liable to pay – and would have paid - under the Liberty Retrocession Cover, but for the Cancellation Notice.
35. Although the Claimant’s Claim in these proceedings was pursued in both contract and in tort, remedies have been awarded to the Claimant in contract. It was not suggested by either party that the remedies in tort would have been different.
B. THE TRIAL
36. Based on the issues addressed in the Defendant’s skeleton argument, the Claimant invited the Defendant prior to the Trial to confirm that several issues which had previously been in contention were no longer disputed. A significant narrowing of the issues by Trial resulted, and the issues narrowed even further during Trial.
37. The day before the Trial commenced, the Defendant indicated that it would no longer be relying on the evidence of Mr Tommy, and his evidence was therefore withdrawn. The Defendant further indicated that it would not need to cross-examine the Claimant’s witnesses Mr Ameer Muhasin and Mr Kumar Vivek Rai, who were already on their journey from Qatar to Dubai for the Trial. Their evidence went to the following:
(a) Mr Muhasin is a senior underwriter for the Claimant. He confirmed that, despite searches undertaken of the email inboxes of the relevant individuals at the Claimant, there were no emails to show that the Claimant knew at any time before the Loss occurred that Liberty was off risk for the second year of cover, or that the Liberty Retrocession Cover needed to be confirmed or renewed.
(b) Mr Rai is the Reinsurance Manager at the Claimant. He responded to the statement in Mr Tommy’s witness statement (now withdrawn) that he was surprised that the Claimant paid the premium under the first year of the Liberty Retrocession Cover without sight of the Liberty Slip. For completeness, Mr Rai’s evidence was that it was common in the market for contracts to be concluded by email where the insurer was dealing with a known and trusted broker, and signed slips can take time to be provided. Confirmation in writing of the cover, along with relevant details, would be sufficient for payment of the premium.
38. The Trial took place over 4 days with factual evidence tendered by the following:
(a) On behalf of the Claimant, Ms Athmadalage Nadeeka Perera, currently the acting General Claims Manager of the Claimant, who became the Claimant’s claims handler dealing with this matter after she joined the Claimant in March 2020. She received a handover on the file from her colleague who was previously dealing with the matter.
(b) On behalf of the Defendant, Ms Maria Kuznetsova, SEO of the Defendant, who became involved in the claims giving rise to this matter on 25 June 2023.
39. Each side appointed an expert in Qatar law:
(a) Mr Salman A Al-Ansari gave evidence on behalf of the Claimant; and
(b) Mr Mohamed L H Al Muhannadi gave evidence on behalf of the Defendant.
40. The scope of evidence given by the experts was wide-ranging. They generally agreed on the core principles and provisions of Qatari law, but disagreed on their application to this case.
41. The Claimant submitted at the conclusion of the Trial that, where Mr Muhannadi’s evidence was inconsistent with that of Mr Al-Ansari, it should be rejected for a number of reasons, including the following:
(a) Mr Muhannadi’s report was written in perfect English. It was said to be written by him in English collaboratively with Mr El Neshef from his firm, despite both being native Arabic speakers. It was then translated by the Defendant into Arabic, in summary form only, and a request was made by the Claimant for Mr Muhannadi to give his evidence in Arabic, with the benefit of an interpreter, based on his not having a strong command of English. The Claimant had requested a witness statement to explain how and why this had happened, questioning the plausibility of this sequence of events.
(b) Mr Frangeskides of the Defendant’s legal team provided a witness statement, which was said to be produced after speaking to Mr Muhannadi, and which Mr Muhannadi had cast his eye over. Mr Muhannadi said in cross-examination that he did not know about this witness statement.
(c) Mr Muhannadi said in evidence that where his report referred to documents which he had reviewed, that did not mean that he had read these documents, just that they were referred to in his report; the fact that the documents were referred to in the report did not necessarily mean that he had looked at them.
(d) Mr Muhannadi could not recall one of the issues which he had been asked to consider in his initial instructions, without referring to his report. He also disagreed with a proposition in his own report until it was shown to him that the words quoted were verbatim from his own report.
42. Based on the points set out above, there is a lack of certainty as to: (i) how much Mr Muhannadi actually contributed to each report; and (ii) the extent to which the reports reflected his views on Qatar law relevant to this case, based on his experience and the relevant facts and documents provided to him. On this basis, I find the evidence of Mr Al-Ansari to be more reliable than that of Mr Muhannadi.
43. However, and in any event, as set out below, there were ultimately not many determinative issues in this case which turned on disputed areas of Qatar law. Further, on a number of issues on which Mr Al-Ansari provided evidence, the Defendant did not adduce any Qatar law evidence in reply.
C. THE ISSUES BEFORE THE COURT
44. It is common ground between the parties that:
(a) The Defendant was obliged under the Contract, and pursuant to Article 136(1) of the Contract Law and/or Article 17 of the Implied Terms Law, to carry out its brokering services with the standard of care and skill which was standard for a reinsurance and/or retrocession broker (the “Contractual Duty”).
(b) The Defendant owed the Claimant a duty of care under the Law of Obligations, the standard of which was that of an ordinary skilled person exercising and professing to have skill as a reinsurance / retrocession broker and/or the care which a person of ordinary care and skill engaged in reinsurance / retrocession broking would have exercised (the “Tortious Duty”).
45. It is also common ground that the Defendant was under a number of regulatory obligations pursuant to the DFSA Rulebook, but the Defendant contests the relevance of these obligations. It is not necessary for me to make any findings about the relevance of these obligations.
46. By Trial, the Defendant no longer relied on any evidence (including witness evidence) to suggest that the Defendant had informed the Claimant of the Cancellation Notice in the Liberty Slip prior to 5 September 2019, having pleaded that the Cancellation Notice “would have been sent” to the Claimant on, or shortly after, 27 July 2018.
47. For the avoidance of doubt, I find that the Cancellation Notice was not sent to the Claimant by the Defendant until 5 September 2019, given:
(a) the absence of any document on the record demonstrating that the Defendant sent the Claimant the Cancellation Notice prior to 5 September 2019, despite both parties seeking specific disclosure of any such documents;
(b) Ms Kuznetova, the SEO of the Defendant, signing a statement of truth dated 2 May 2025 confirming that the Defendant had searched for all documents by which the Cancellation Notice was sent to the Claimant prior to 5 September 2019, but had not been able to locate any document responsive to the request. The Claimant had similarly conducted a search for such a document, with none being found.
48. In relation to the standard of care and particulars of breach of duty, the Defendant does not admit the Claimant’s categorisation of the standard of care or the particulars of breach alleged against the Defendant, but it does not deny those particulars, nor did it advance any alternative case at Trial.
49. By Trial, the Claimant’s principal case on breach of duty was encapsulated in the pithy summary that the Defendant breached its Contractual Duty and Tortious Duty to the Claimant by:
(a) failing to procure cover on the back-to-back terms sought, i.e. retrocession for the Reinsurance, because the Liberty Retrocession Cover was subject to the Cancellation Notice, pursuant to which the Claimant was left without cover in the second year of the Reinsurance; and
(b) failing to inform the Claimant that the Liberty Retrocession Cover was subject to the Cancellation Notice.
50. The Claimant’s case rests on the assumption that the Cancellation Notice in the Liberty Slip was effective. This is not admitted by the Defendant, and I address this issue first below, before addressing the standard of care and alleged breach of duty.
51. On causation and loss, the Defendant’s position is that, even if breach is established, it is not liable to the Claimant for any loss because:
(a) No prima facie coverage: The Defendant does not admit that HOC2 and HOC3 are prima facie covered under the Underlying Insurance under Qatar law (and therefore by implication under the Reinsurance or Retrocession Cover). The Defendant did not submit Qatar law evidence on this point, but sought through its cross-examination of Mr Al-Ansari to demonstrate that HOC2 and HOC3 are not prima facie covered under the Underlying Insurance.
(b) Insufficiency of Claim Documentation under Article 790 Qatar Civil Code: The Defendant contends that, pursuant to Article 790 of Qatar Civil Code, any obligation which Liberty would have to pay an indemnity under the contract of retrocession has not crystallised by reason of the absence of, and inconsistency between, the claim documents which were provided to support the claims pursuant to the Underlying Insurance (and, in turn, under the Reinsurance). It contends that Liberty’s obligation to indemnify would not have arisen on this basis.
(c) Material Non-Disclosure: The Defendant contends that the Underlying Insureds failed to disclose to Doha (and Doha failed to disclose to the Claimant) a previous AC unit fire at the Superyacht Facility. Part of the Defendant’s case is that it is possible that the fire which caused the Loss was caused by an AC unit, notwithstanding a finding to the contrary in a Qatari police report which was before the Qatari Court of First Instance in a related claim. The Defendant relies on Articles 781 and 782 of the Qatar Civil Code and contends that the non-disclosure was a breach of the duty of good faith under Qatar law which annulled (in whole or in part) the Underlying Insurer’s and the Claimant’s obligation to pay an indemnity under the Underlying Insurance and Reinsurance respectively, and reduced the premium which would be payable. An application was made at Trial by the Defendant to admit the expert evidence of an underwriting expert supporting the Defendant’s position that a reduced premium would be payable under the Liberty Retrocession Cover if it had remained in place, and for this issue to be heard at a further one-day hearing. The Claimant opposed the application, and denies that the material non-disclosure defence arises as a matter of both fact and law.
52. An overarching argument raised by the Claimant is that all the points raised at paragraph 51 above are “ambitiously novel” defences which no other party involved in the insurance scheme has taken, given that all the other insurers have paid out on identically worded policies, which are also governed by Qatar law.
53. Critically, the Claimant relies on the fact that Liberty itself participated in – and paid out under – another part of the insurance scheme, namely the AON Reinsurance. The Claimant submits that the Defendant’s defences therefore have a fundamental flaw: even if Liberty had a defence under the Liberty Retrocession Cover as a matter of Qatar law, that is irrelevant, because as a matter of causation, Liberty was 100% likely to pay an indemnity in any event, because Liberty did so on the materially identically worded AON Reinsurance that it participated in.
54. The Defendant denies that the Claimant’s loss of chance analysis is correct as a matter of law.
55. The Claimant also claims that, where QBE exercised claims control, then pursuant to Qatar law, QBE became the legal decision maker on documentation sufficiency, and all parties in the chain are bound by those determinations under good faith principles, absent fraud or manifest error. The Defendant disagrees with the Claimant’s analysis under Qatar law, and this issue is a key area of contention between the parties’ experts.
II. STANDARD OF CARE AND BREACH OF DUTY
56. The only issue actively contested by the Defendant at Trial on standard of care and breach of the Contractual Duty and the Tortious Duty was whether the Cancellation Notice in the Liberty Slip was effective. I address that issue first.
I. Was the Cancellation Notice in the Liberty Slip effective?
57. There is no dispute as to the applicable principles of contractual construction under Qatar law, as follows (in translation):
“Article 65
1. The expression of will may be made verbally, in writing, by commonly used gestures, through acts indicating consent, or by any other conduct that leaves no doubt under the circumstances as to the true intention of the person.
2. The expression of will may also be implicit, unless the law, agreement, or the nature of the transaction requires it to be explicit.
Article 169
1. If the wording of the contract is clear, it shall not be deviated from in interpreting the parties' intent.
2. If interpretation is required, the common intention of the contracting parties must be sought, without limiting consideration to the literal meaning of the words, taking into account the nature of the transaction and the required good faith and trust between the parties, in accordance with customary practices in transactions.
Article 171
1. A contract constitutes the law between the parties, and it may not be annulled or modified except by mutual agreement of the parties or for the reasons prescribed by law.
2. However, if exceptional general events occur that could not have been anticipated, and as a result, the performance of the contractual obligation, while not impossible, becomes excessively burdensome for the obligor to the extent of threatening them with substantial loss, the judge may, depending on the circumstances and after balancing the interests of the parties, reduce the onerous obligation to a reasonable level. Any agreement to the contrary shall be void.
Article 172
1. A contract must be performed in accordance with its provisions and in a manner consistent with good faith.
2. The contract is not limited to binding the parties to what is explicitly stated therein, but also extends to what is implied as necessary for its performance, in accordance with the law, custom, and principles of fairness, depending on the nature of the obligation.”
58. The Defendant submits that the Cancellation Notice is premised on:
(a) The giving of 30 days notice, to take effect from the anniversary of the inception of the insurance; and
(b) There being an agreement, or at least a negotiation, as to the rate of premium and/or conditions and/or warranties
59. The Defendant argues that the purpose of the clause is to enable the parties, underwriters and assured to assess the performance of the contract during the first 11 months, and see whether they are prepared to continue and on what terms. It is for that reason that the clause envisages a 30-day notice period, and not a 365-day notice period.
60. The Defendant further argues that by the use of the word “deemed”, meaning “to be treated as”, the Cancellation Notice does not purport to be an actual notice.
61. In response, the Claimant:
(a) submits that the Defendant does not admit the validity of the Cancellation Notice, but has never submitted a positive case in this regard, nor served any Qatar law evidence on this issue;
(b) relies on the evidence of the Claimant’s appointed Qatar law expert, Mr Al-Ansari, to the effect that the fact that more notice than required was given under the Cancellation Notice was a benefit to the recipient, and nothing in Qatar law prevented that;
(c) submits that the Claimant’s argument taken to its logical conclusion would mean that a notice given 30 days and one minute in advance is invalid. In response to the Defendant’s clarification that, on its construction, “30 days”, means “approximately” 30 days, within a reasonable tolerance, the Claimant submits that such a construction remains absurd;
(d) points out that in the correspondence between Mr Tommy and Mr Reinhardt of the Defendant with the Claimant in October 2018, the Defendant acted consistently with the Cancellation Notice being valid, and did not suggest that it was invalid. Further, that the basis of the Defendant’s professional negligence claim against LPIB in the Commercial Court in London is that the Liberty Slip was only for one year rather than two years’ worth of cover.
62. In relation to the use of the word “deemed”, the Claimant submits that “deemed” refers to the date the Notice was given (in other words, it was deemed to be given at inception of the risk).
63. The Defendant submits that there is no conceivable way in which a retroactive notice of that nature could be said to be a proper notice under LSW196A, as it could not take effect from a retroactive date.
64. The Court’s decision on this issue is that the Cancellation Notice is valid. For ease of reference, the operative part of the clause is set out here:
“Notwithstanding that this insurance is for a period of [24] months, it may be cancelled by either the Underwriters or the Assured giving 30 days notice to take effect from the time of the anniversary of the inception of this insurance.”
65. The purely literal construction of the clause is that 30 days notice must be given of cancellation. However, I do not accept a literal meaning that exactly 30 days notice must be given, and reject it as implausible and unworkable. For the same reasons, I reject the Defendant’s argument that the clause must mean “approximately 30 days” with “a reasonable tolerance”.
66. Pursuant to Article 169(2) of the Qatar Civil Code (as translated), I must construe the clause by interpreting “the common intention of the parties, taking into account the nature of the transaction and the required good faith and trust between the parties, in accordance with customary practices in transactions”. Adopting this approach, I have no doubt that the clause requires “at least” 30 days notice, with there being no bar on notice being provided at inception, approximately a year in advance of the intended cancellation. With this construction in mind, I accept the evidence of the Claimant’s expert Mr AlAnsari that the “…Cancellation Notice is valid and effective under Qatari law”.
67. The Defendant’s argument that the Cancellation Notice could not have been deemed to be given at inception was not persuasive, and I am mindful that Mr Tommy of the Defendant wrote to the Claimant’s Mr Alterhi on 17 September 2019 stating, “the notice of cancellation is deemed to have been given at inception of reinsurance irrespective of change in terms and rates”.
II. What is the Standard of Care for the Contractual Duty and Tortious Duty?
68. It was not clear at Trial whether the Defendant disputed or even continued to “not admit” the particulars advanced by the Claimant on the standard of care, with the Defendant’s lead Counsel submitting “I don’t think it is likely to be a live issue”.
69. For the avoidance of doubt, I accept, as submitted by the Claimant, that the relevant principles and authorities on the standard of care for the Contractual Duty and Tortious Duty are as follows:
(a) Insurance brokers are required to exercise the degree of skill and care which is exercised by reasonably competent insurance brokers (Jackson & Powell on Professional Liability (9th ed.) at [16-037]).
(b) In general terms, an insurance broker’s duties are as summarised in Jackson & Powell (9th ed.) at [16-044] (quoted substantially with approval in Dalamd Limited v Butterworth Spengler Commercial Limited [2018] EWHC 2558 (Comm) at [80]):
“…2. the broker should take reasonable steps to arrange the insurance cover which the client has instructed him to obtain, and which is suitable for and clearly meets the client’s requirements;
…
4. if the broker is unable to arrange the requested cover, then he should advise the client as to the scope of cover that has and has not been arranged;
5. once the cover has been placed, the broker should consider and explain to the client what cover has been arranged; and
6. at renewal of an existing policy, the broker should go through the same exercise that was carried out at the inception of the policy.
Most of the cases in which a broker has been found liable for breach of duty are ones where the broker has failed to act with due skill and care in the performance of one of those steps.”
(c) The duty to exercise reasonable skill and care involves the duty to procure the cover sought by the client. In the context of reinsurance, a broker must usually ensure that the risk reinsured is defined in identical terms to the risk covered by the primary insurance, with any failure to do so being a breach of his express instructions and, almost inevitably, negligent: Jackson & Powell (9th ed.) at [16-058].
(d) In Youell v Bland Welch & Co Ltd (No 2) [1990] 2 Lloyd’s Rep 431 (the “Superhulls Cover” case), the reinsurance which was obtained for building risks insurance included a 48-month cut-off clause which was not present in the underlying insurance. The brokers failed to inform the insurers about the 48-month cut-off clause. Phillips J found the brokers negligent on a number of grounds, including for obtaining cover which was not in accordance with the reinsurance cover ordered, and for failing to inform the insurers that the reinsurance cover obtained for the insurance was subject to the cut-off (at p. 446).
(e) A broker should keep the client properly informed as to the presence or absence of cover, and if he is unable to effect insurance on the specific terms required, he is under a duty to notify the client promptly: Jackson & Powell (9th ed.) at [16-109]. If the client becomes uninsured for any reason, they should be notified as a matter of urgency: Jackson & Powell (9th ed.) at [16-113].
(f) Bromley v Ellis [1971] 1 Lloyd’s Rep 97 (at p.99) is an example of a case in which a broker was found to be in breach of its duty of care to the insured in failing to advise the insured of the cancellation of the relevant insurance policy:
“The Judge found that the brokers were at fault. They failed to advise Mr. Ellis of the letter of Dec. 19, saying that insurance would be cancelled in seven days. I quite agree that this was a serious fault on the part of the brokers. But I would put it more generally. The brokers were, I think, under a duty of care to look after Mr. Ellis's interests. […] They failed in many respects, one after the other. […]”
(g) As an agent under the Contract, the Defendant was bound to act with care and skill and solely for the benefit of the Claimant in all matters connected with its agency, pursuant to Articles 136-137 of the Contract Law.
III. Did the Defendant breach the Standard of Care?
70. The principal breaches alleged against the Defendant are as set out at paragraph 49 above. The Claimant pleaded several other particulars of breach, but submitted at Trial that these would be unlikely to add materially to the principal allegation concerning the Defendant’s failure to procure back-to-back retrocession coverage. The Claimant’s additional breaches of duty alleged can be summarised as follows:
(a) The Defendant failed to inform the Claimant on the expiry of the first year of the Liberty Retrocession Cover (1 June 2019) that it was no longer covered. Further, the Defendant failed to ensure that there were no gaps in the coverage obtained for the Claimant, and failed to guard against unnecessary exposure to risk.
(b) The Defendant failed to obtain or take steps to procure extensions to the Liberty Retrocession Cover.
(c) The Defendant generally failed to act with due skill, care and diligence.
71. I have no hesitation in finding that the Defendant breached its Contractual Duty and Tortious Duty to the Claimant as alleged at paragraphs 49 and 70 above for the following reasons:
(a) It was understood by Mr Tommy of the Defendant that the Claimant wished to procure retrocession cover on the same basis as the Reinsurance, based on Mr Alterhi’s instructions to him by email of 15 July 2018, attaching the Reinsurance.
(b) Mr Tommy stated in an email to Mr Alterhi of 23 July 2018 that Liberty would write 5% of the retrocession risk, on the terms of the AON Slip.
(c) Once he received the Liberty Slip from LPIB on 27 July 2018, Mr Tommy failed to forward it to the Claimant. Critically, he failed to bring to the attention of the Claimant the fact that, through the Cancellation Notice, the period of cover under the Liberty Retrocession Cover ended on 31st May 2019, after one year, and therefore did not dovetail with the 2 year Reinsurance.
(d) This failure appears to have been compounded by Mr Tommy’s confirmation to Mr Alterhi by email of 28 October 2018 that the retrocession coverage brokered by the Defendant was for 2 years.
(e) The Cancellation Notice was not brought to the attention of the Claimant until 5 September 2019, after the Loss had occurred.
(f) The Defendant failed to procure back-to-back coverage for the Claimant and failed to ensure that there were no gaps in the coverage obtained by the Claimant. The Defendant therefore failed to guard against unnecessary exposure to risk by the Claimant. No steps were taken by the Defendant to fill the gaps in the Claimant’s retrocession cover for the Reinsurance.
E. CAUSATION AND LOSS
72. The Defendant’s position is that, on any basis, the insurance claims in this matter are large, with the cost of repairing the Superyacht Hall alone - before a decision was taken to indemnify the loss on an unrepaired basis - having been estimated at a cost in excess of USD 100 million. The Defendant submits that the claims would have merited “the fullest scrutiny and loss adjustment”, but the Claimant, as cedant, instead appears to have performed nothing more than “a box ticking exercise” by relying on the loss adjustment carried out by QBE as the leading underwriter on the AON Reinsurance, which was a different contract of reinsurance.
73. It should be noted that the Defendant sought disclosure of the loss adjuster files in this case, but QBE was not forthcoming with these files, such that disclosure of the underlying claim and loss adjustment documents, including settlement agreements, was piecemeal. One tranche of documents was disclosed on 19 March 2025, and two tranches of the disclosure took place on 15 August 2025 and 17 November 2025 – after the Defendant’s Amended Defence of 18 July 2025.
I. Is there prima facie cover under the Underlying Insurance?
74. The Defendant admits that HOC1 – the loss of the yachts – is prima facie covered under Section 1 of the Underlying Insurance. The Defendant does not accept that HOC2 (relating to the costs of dismantling and removing the damaged superyachts, and costs associated with the claim), and HOC3 (the claim for unrepaired damage to the Superyacht Hall) are prima facie covered by Section 1 of the Underlying Insurance. The Defendant also denies that HOC2 and HOC3 are covered by Section 2 (although, in fact, the Claimant does not assert that HOC2 is covered under Section 2).
75. The Claimant submits that the HOC2 losses are covered under Section 1 of the Underlying Insurance, and that the HOC3 losses are covered under both Section 1 and Section 2. It relies on the evidence of its Qatar law expert, Mr Al-Ansari, to support its position, pointing out that there is no Qatar law evidence relied upon by the Defendant to substantiate the points it advances.
Section 1 of the Underlying Insurance
76. Section 1 includes the following at Clause 6 of the LSW169A wording:
“6. COVERAGE
Underwriters hereby agree, subject to the limitations, terms and conditions hereinafter mentioned to indemnify the Assured for all sums which the Assured shall become liable to pay by reason of the legal liability of the Assured as ship repairers for:-
I. Loss of or damage to any vessel or craft which is in the care, custody or control of the Assured for the purpose of being worked upon including shifting and moving within the limits of the port at which the work is being carried out and including trial trips but not exceeding 100 miles from such port;
II. Loss of or damage to any other vessel or craft upon which the Assured is working except vessels or craft at sea other than whilst on trial trips;
III. Loss of or damage to cargo or other things on or discharged from any of the vessels or craft referred to in (i) or (ii) above;
IV. Loss of or damage to machinery or equipment of any vessel or craft, whilst such machinery or equipment is removed from such vessel or craft and is in the care, custody or control of the Assured for the purpose of being worked upon, including whilst in transit between such vessel or craft and the premises;
V. Removal of wreck;
VI. Loss of or damage to third party property occurring in the course of or arising from the ship repairing operations of the Assured, where such liability results from negligence of the Assured, his servants, agents or sub-contractors occurring during the period of this insurance.”
77. Section 1 was amended with respect to the following exclusion at Clause 9(i) under the LSW169A wording:
“9. EXCLUSIONS
Notwithstanding anything contained herein to the contrary, this insurance shall not cover any liability:-
(i) in respect of property
(a) owned by, used by or leased to the Assured;
(b) in the care, custody or control of the Assured (other than property referred to in Clause 6(i), (iii) or (iv) above)”
78. The relevant amendment provides “Amended to remove Exclusion 9(i) in respect of Qatar Petroleum’s property which is leased, occupied or in the care, custody and control of NDSQ”.
79. The Defendant argues that the following cross-liabilities clause (the “General Cross-Liability Clause”) is included in Section 2 of the Underlying Insurance but not Section 1, because it is mentioned in the summary of original conditions (“Summary”) provided at the beginning of the policy in relation to Section 2, but not in the Summary for Section 1:
“CROSS LIABILITY CLAUSE
It is hereby understood and agreed that in the event one of the Assures incurring liability to any other of the Assureds this policy shall cover the Assured against claim is or may be made in the same in the same manner as if separate policies had been issued to each Assured, but this clause shall not operate to increase Underwriter’s limit of liability under this policy.”
80. The Defendant points out that the definition of “third party” in the Underlying Insurance excludes an Underlying Insured or its subsidiary, but the General Cross-Liability Clause enables property of a co-assured to be treated as being property of a “third party”.
81. In relation to HOC3, the Defendant submits that if one co-assured has a claim against another co-assured, then absent the General Cross-Liability Clause, both fall within the definition of “insured” under the policy, and damage to the Superyacht Facility would not comprise damage to third property under clause 6(vi). The Defendant submits that the General Cross-Liability Clause is not included in Section 1 of the Underlying Insurance, although the AON Slip mistakenly refers to Section 1 including a cross-liabilities clause.
82. The Defendant’s submission on HOC2 is that HOC2 concerns damages to the yachts which were in the “care, custody or control of the assured”, and therefore caught by the exclusion under Clause 9(i). The Defendant also relies on the absence of a General Cross-Liability Clause for HOC2, and although not specifically articulated, the Defendant presumably argues that any damage to QE’s property would in any event not be covered under Section 1 because such property would not be considered that of a “third party” in the absence of a General Cross-Liability Clause.
83. The Claimant’s response to these arguments under Section 1 is to rely on the following points, which were referred to in Mr Al Ansari’s reports and oral evidence:
(a) the General Cross-Liability Clause was in fact included in Section 1 and therefore applicable to both HOC2 and HOC3;
(b) In relation to HOC2:
I. “wreck removal” is explicitly covered under Clause 6(v) of Section 1; and
II. The removal of the wrecked yachts is in any event “inextricably linked” to the damage to the Superyacht Facility, with the structures of the hulls enmeshed with the structure of the hall. In the Claimant’s submission, this practical reality is reflected in:
1. the law - in relation to which the Claimant relies on the evidence of Mr Al Ansari in cross-examination that “the wreck will be in the hall itself and within the properties of Qatar Petroleum… so eventually, the hall itself, and whatever within, is impacting Qatar Petroleum."
2. the factual evidence - in relation to which it relies on the Sedgwick report of 18 August 2019 which includes the following:
"The building structure facilities included various gantry cranes mounted on secondary steel gantry rails and have been damaged to varying degrees due to both the fire and the weakening of the structure. At the time of our initial attendance ... 2no of the gantry cranes had collapsed and had come to rest against the scaffolding surrounding the yachts. As of the date of our inspection inside the building…
a further gantry crane had collapsed bringing some of the secondary steel gantry rails and building cladding down with it.”
84. In relation to the General Cross-Liability Clause, the Claimant accepts that in the Summary of Section 1 in the Underlying Insurance, there is no reference to any crossliabilities clause, whilst there is such a reference in relation to Section 2. The Claimant submits, however, that one needs to read the policy as a whole, and the specific policy clauses are appended to the policy in a section entitled “Wording & Clauses” (the “Policy Wording”). The Claimant submits that the General Cross-Liability Clause appears at the end of the Section 1 Policy Wording, and the Section 2 Policy Wording includes another cross-liabilities clause.
Court’s Decision on Section 1
85. I accept the Claimant’s submission that Section 1 includes the General Cross-Liability Clause, even though it is not included in the Section 1 Summary, for the following reason:
(a) The final three conditions listed in the Section 1 Summary are “Personal Injury Endorsement”, “Hot Works Warranty” and “Primary Insurance Clause”.
(b) The Section 2 Summary then begins with a brief description of the Section 2 coverage, followed by a reference to “Excess Liability Claims Made Policy – LSW 244, as attached”.
(c) In the Policy Wording following the Summary of each Section, the General CrossLiability Clause appears after the “Personal Injury Endorsement”, “Hot Works Warranty” and “Primary Insurance Clause” and this is immediately followed by the Section 2 Policy Wording, beginning with the clauses of the “Excess Liability Claims Made Policy – LSW 244”. This placement of the General Cross-Liability Clause, in the same section as the Section 1 Policy Wording, before the Section 2 Policy Wording commences, suggests that it is incorporated in Section 1 of the Underlying Insurance.
(d) The fact that Section 1 was specifically amended to provide cover “in respect of Qatar Petroleum’s property which is leased, occupied or in the care, custody and control of NDSQ”, suggests that the General Cross-Liability Clause applies to Section 1.
86. I also accept that the wreck removal costs claimed under HOC2 are explicitly covered under Clause 6(v) of Section 1 of the Underlying Insurance which states that the Underwriters agree to indemnify for “Removal of Wreck”.
87. This is so notwithstanding Exclusion 9(i)(b) which excludes liability in respect of property in the care, custody or control of the assured (other than property referred to in Clause 6(i), (iii) or (iv) above, or QE property leased, occupied or in the care, custody and control of NDSQ). I find that “removal of wreck” is a separate head of damage to liability for the yachts (which is separately covered under Clause 6(i)), and reject the Defendant’s argument that removal of the wreck concerns damage to the yachts and is therefore caught by the exclusion. I accept Mr Al-Ansari’s evidence that Clause 6(v) expressly covers wreck removal and therefore covers HOC2.
88. I also accept the Claimant’s submission, based on the oral evidence of Mr Al-Ansari and the 2019 Sedgwick report, that the removal of the wrecked yachts was “inextricably linked” to the damage to the Superyacht Facility and would therefore, in any event, fall within the exception for QE’s property.
Section 2 of the Underlying Insurance
89. The Section 2 Summary includes the following (with emphasis added):
“This insurance shall cover the third party legal and contractual liability of the Insured to pay damages, costs and expenses as a result of loss or damage to property, death, bodily injury suffered by any person not engaged in the service of the Insured, including indemnity obligations in respect of similar losses under the contracts described herein, or similar contracts entered into by NDSQ.
.....
Including liability for loss and/or damage to the property of Qatar Petroleum, under the Access and Indemnification Agreement, including Property leased, occupied or in care, custody and control of the Insured.”
(I shall refer to the second paragraph above as the “QE Property Provision”).
90. The Defendant submits that liability arising under HOC3 for unrepaired damage to the Superyacht Facility would be covered under the provisions referred to above, provided the liability arose under the Access and Indemnification Agreement, which includes a lease indemnity.
91. The Defendant refers to the “curious” Settlement Agreement disclosed in draft between QE, Nakilat and NDSQ, which refers to wreck removal to be carried out by QE pursuant to an “Agency Agreement” between QE and Nakilat. The Defendant submits that it would have to be proved that the Agency Agreement was a “similar contract entered into by NDSQ” and it would almost certainly have to be disclosed to underwriters. This submission appears to be directed towards HOC2 not being covered under Section 2. Since this is not part of the Claimant’s case, I do not address it further.
92. I should mention that the Section 2 Summary refers to “Cross Liability Clause as attached”. The cross liabilities clause which is included in the Section 2 part of the Policy Wording is different from the General Cross-Liability Clause, as it is specifically directed at personal injury claims. The clause included in the Section 2 Policy Wording (the “Personal Injury Cross Liability Clause”) provides as follows:
“CROSS LIABILITY
In the event of claims being made by reason of Bodily Injury suffered by any employee of one Insured which does not arise out of the injured employee’s employment, for which another Insured is liable, then this policy shall cover the Insured against whom such claim is made in the same manner as if separate policies had been issued to each Insured.”
93. Similarly, the “Primary Insurance Clause” is included in the Section 2 Summary but not included in the Section 2 part of the Policy Wording. I consider it likely that Section 2 includes both the Primary Insurance Clause and the General Cross-Liability Clause from the Section 1 part of the Policy Wording, even though they are not specifically set out in the Section 2 part of the Policy Wording.
94. Section 2 likely includes the General Cross-Liability Clause because of the express QE Property Provision included in the Section 2 Summary providing that it includes liability for “loss and/or damage to the property of Qatar Petroleum, under the Access and Indemnification Agreement…”
95. Even if I am wrong about the General Cross-Liability Clause being included in Section 2, it is clear from the QE Property Provision that damage to the Superyacht Facility owned by QE would in any event be specifically covered under Section 2, and I accept Mr Al-Ansari’s evidence that the provision “provides clear coverage for damage to QE’s property”.
96. In any event, I find that HOC3 would be covered under either Section 1 or Section 2 of the Underlying Insurance.
II. Would Liberty’s obligation to indemnify have arisen by reference to Article 790 of the Qatar Civil Code?
The Law
97. The parties agree that Article 790 of the Qatar Civil Code, which provides as follows (in translation), is the starting point when considering an insurer’s obligations:
“Upon the occurrence of the insured risk or the maturity of the premium under the contract, the insurer shall pay the insurance amount due within thirty (30) days from the date on which the beneficiary provides the required statements and documents in support of his right.”
98. The parties further agree that there is a general evidential burden on an insured to submit documents in support of its claim, and that insurers are required to make payment within 30 days from the date on which the beneficiary provides the required statements and documents in support of his right.
99. Article 172 of the Qatar Civil Code provides in translation that all contracts (including insurance and reinsurance contracts) must be performed “consistent with the requirements of good faith”. The parties agree that, at the post-loss stage, good faith requires the insured to submit all relevant and truthful documentation necessary to establish the claim, as required by Article 790.
100. The Defendant sought to persuade the Court that only certain specific documents would satisfy the requirement under Article 790, although there were no specific authorities setting out prescribed documents, and the experts agree that the Qatar Civil Code does not address the nature or form of the evidence that must be submitted to substantiate a loss. The Claimant argues that what is required to satisfy Article 790 is fact-sensitive and not capable of general definition, and I accept this.
101. I also accept the evidence of Mr Al-Ansari that, if documents supporting a claim under Article 790 cannot be produced because they are withheld by a third party, the insured must show reasonable diligence in seeking them and provide notice to the insurer. Further, that the absence of documents alone does not extinguish the insured’s right to a claim unless there is a clear failure to act reasonably and in good faith. This is based on Article 776 of the Qatari Civil Code, which provides that where non-performance is based on an external cause outside of the insured’s control, and provided the insured acts in good faith, forfeiture of rights can be avoided.
102. The Defendant argues that there is no completed cause of action under Article 790 until the required statements and documents are supplied, such that the claim crystallises on the provision of the documents. The Claimant denies this, averring instead that Article 790 stipulates what is deemed to be a reasonable period for the payment of the claim by the insurer, and the policyholder’s cause of action crystallises upon the occurrence of the insured risk. It is not clear what, on the Defendant’s case, turns on this distinction. In any event, the Defendant’s own expert Mr Muhannadi agreed that, under Qatar law, the insured’s cause of action arises upon the loss, and I find this to be position:
“…[w]hile Article 790 confirms that the indemnity becomes due upon occurrence of the insured event, it also presupposes that the insured provides complete documentation to substantiate the claim. The cause of action arises upon the loss, but the obligation to pay an indemnity is suspended until there is evidentiary completeness which is a substantive part of the Insurer’s obligation”.
103. Both experts agree that good faith governs the insurer’s conduct in claims handling and settlement, and that the insurer must evaluate the claim promptly, communicate any additional information required, and pay the indemnity within the statutory period. Delay or obstruction without legitimate cause would constitute bad-faith performance under Article 172 and may give rise to compensation under Article 256 for delay in contractual performance.
The Facts and The Defendant’s Application to Amend
104. The Defendant’s pleaded position in the Amended Defence was that “[i]n the absence of properly documented claims in respect of damage and cost associated with the alleged fire, there was no cause of action under the Underlying Insurance and/or Reinsurance”. The Defendant had attached to its skeleton argument a 15-page schedule of alleged documentary absences and inconsistencies (the “Schedule”), which the Claimant averred did not reflect the Defendant’s pleaded case. On the third day of the four-day trial, at the close of oral evidence, the Defendant applied to amend the Amended Defence to add in a reference to the Schedule which particularised the absence of properly documented claims.
105. The Schedule set out a number of documents relevant to HOC1, HOC2 and HOC3 and pointed out discrepancies and gaps which the Defendant averred showed a lack of substantiation for the losses claimed. In particular, the Defendant submitted that its points on the following three documents were critical to its case:
(a) Burgoynes (consulting scientists and engineers) “Initial Advice” dated 28 August 2019 investigating the cause of the fire on 11 August 2019 and requesting certain documents and samples (“Burgoynes Investigation Report”);
(b) IFIC Forensics “Report into the Origin and Cause of the Fire at [the Superyacht Hall]” dated September 2019 setting out documentation that IFIC Forensics had not received, and requesting documents (the “IFIC Investigation Report”). The IFIC Investigation Report concludes that the fire was most likely caused by an electrical defect within an AC unit situated on a scaffolding tower on the Starboard side of the vessel Constellation; and
(c) The Yachts Settlement Agreement of August 2020.
106. The Defendant argued that the Claimant would not have any evidence to file in relation to these reports – and therefore no possible prejudice could be caused by the late amendment - because these were documents in the possession of Qatar Energy that the Claimant previously did not have access to in any event. By contrast, if the amendment were not allowed, the real dispute between the parties would not be adjudicated on.
107. The Schedule also included “requests for clarification” on various invoices relating to the insurance claims. The Defendant suggested that the Claimant provide an explanation on the invoices by way of a counter-schedule to be submitted in due course.
108. The Defendant argued as follows:
(a) The prejudice to the Defendant if the application were not allowed would be substantial because a key part of its case would be shut out.
(b) However, there would be no prejudice to the Claimant because the Claimant’s expert Mr Al-Ansari had indicated in evidence that he did not feel able to give an opinion on documentary sufficiency or adequacy. All the matters to be addressed could be made by way of submissions at closing, particularly in relation to the points on the three documents identified as critical by the Defendant.
(c) The Defendant denied the Claimant’s submission that the Schedule did not meet the standard of clarity and detail required to be part of a pleading and that it was “extraordinary” that it was put forward as one. The Defendant submitted that it was clear how the discrepancies and gaps alleged in the Schedule were relevant to the Defendant’s case that insufficient documentation was provided to support each claim under the Underlying Insurance.
109. The Claimant submitted that the relevant test for the Court to apply was that set out in the well-known case of Qua Su-Ling v Goldman Sachs [2015] EWHC 759 (Comm) decided by Mrs Justice Carr (as she then was) in which she held:
"Very late applications for permission to amend in circumstances where (a) there is no good reason for the delay and (b) amendment would result in real disruption or prejudice to the parties and/or the Court are unlikely to be allowed, irrespective of the merits of the proposed amendment."
110. Applying the test, the Claimant submitted that:
(a) There was no good reason for the delay, and no evidence was filed by the Defendant to suggest there was.
(b) 23 of the documents referred to in the Schedule were disclosed on 19 March 2025; 17 on 15 August 2025, 1 in October 2025; and 3 on 17 November 2025. Therefore, 60% of the proposed amendments could have been made shortly after production in March 2025; over 90% could have been made after 15 August 2025; and all of the amendments could have been made by December 2025. Yet the application to amend was made on Day 3 of the Trial, in January 2026, with no explanation as to why.
(c) The amendments would cause significant disruption and prejudice to the parties and the court. The Claimant would not have an opportunity to reply to the amendments, nor would it have an opportunity to file evidence in response to the allegations, for example from its factual witness.
(d) Further, it was not clear why documents relevant to HOC3 were included in the Schedule. The HOC3 claim has not yet been paid under the Underlying Insurance, such that it cannot not be said at this stage that insufficient documentation has been provided in support of the claim.
Court’s Decision on the Application to Amend
111. Under RDC 18.2, a statement of case may only be amended with the written consent of all other parties, or with the Court’s permission. RDC 18.15 provides that “[l]ate amendments should be avoided and may be disallowed”.
112. There was no dispute as to the applicable principles, with the Court required to conduct a balancing exercise between the injustice to the applicant if the amendment is refused, and injustice to the opposing party and other litigants in general if the amendment is permitted.
113. The Court rejected the application on the basis that it was filed too late. In dismissing the application, the Court considered the following:
(a) There was no good reason for the late timing of the application and no reason was provided by the Defendant. Whilst it was true that the amendments resulted from disclosure provided by the Claimant, the majority of the documents were disclosed by 7 March 2025 and almost all of them by 15 August 2025. Even if the Claimant had waited until all the documents relied on in the Schedule had been disclosed, the application could have been made in advance of the Trial.
(b) The amendment risked significant prejudice to the Claimant, who would have been deprived of the opportunity of: (i) time to consider its position in response to the amendment; (ii) an opportunity to plead a reply to the amendment; and (iii) the opportunity to adduce evidence in response to the amendment. The Court was not in a position to find definitively that the Claimant’s factual witness (or expert witness) would not be able to comment on the matters raised by the amendment, and that therefore no possible prejudice could be caused to the Claimant, as argued by the Defendant.
(c) As a purely practical matter, the Schedule raised various queries on invoices which the Defendant requested the Claimant to respond to, and it was not clear when there would be an opportunity for such responses to be provided, given that the Trial would conclude the following day.
(d) Balancing the potential injustice to the Defendant if the amendment were disallowed against the potential prejudice to the Claimant, the Court considered the late application should be disallowed.
Would Liberty have been entitled to deny liability pursuant to Article 790 on the basis of insufficiency of documentation?
114. With the Defendant’s application to amend having been dismissed, the Defendant was left with a fairly bare pleading that, in the absence of properly documented claims in respect of damage and cost associated with the alleged fire, there was no cause of action under the Underlying Insurance and/or Reinsurance. Further, that the Underlying Insurer and Underlying Insureds breached their duty of good faith in making and/or paying a claim on the basis of inadequate evidence, annulling (in whole or in part) the Underlying Insurer’s and Claimant’s obligation to pay an indemnity under the Underlying Insurance and Reinsurance respectively.
115. The only example pleaded of insufficient documentation related to works for demolishing and rebuilding the damaged Superyacht Hall. A decision was eventually taken by QE not to rebuild the Superyacht Hall, such that this element of the claim under HOC3 will be on an unrepaired damage basis. This has rendered the Defendant’s specific example of insufficient documentation irrelevant.
116. The Defendant nevertheless sought to make good its general allegations of insufficient documentation.
117. Ms Perera’s evidence was not especially probative in this regard, which is perhaps not surprising as she essentially passed correspondence and information relating to the Underlying Insurance claims up the chain to the Defendant as she received them, and relayed queries back down the chain (although Ms Kurnetzkova sought to convey in her evidence that she did not do so very actively). QBE was the lead insurer exercising claims control over Doha and handling the claim (along with any second agreement party, which is addressed further below). Ms Perera’s role was therefore limited, although she gave evidence that the Claimant internally checked that payment requests were properly supported.
118. Ms Kurnetzkova’s evidence sought to establish “multiple instances of… lack of information and sporadic reporting” by the Claimant. However, her evidence fell far short of substantiating the Defendant’s general allegation of insufficient documentation for the following reasons:
(a) Ms Kurnetzkova joined the Defendant in 2023, and there were a number of instances of her asking for information and documents that had already been provided by the Claimant to the Defendant prior to her joining. Whilst she was an earnest witness, she struggled to answer questions directly in an apparent desire to be helpful and provide as much explanation as possible. She did not respond directly when asked whether she reviewed the file for this matter upon joining the Defendant, but it was clear that she had not with her explanation “when you become SEO of the company, you have a lot of other tasks to do”. The result was a number of queries in correspondence to the Claimant that ultimately came across as confused since it transpired that the information and documents sought had in fact already been provided.
(b) This was the case even for information which had been provided to Ms Kurnetzkova after she joined the Defendant. For example, she stated in her witness statement that, on 14 October 2025, Doha explained to the Claimant that they were maintaining a balance reserve of USD 35 million, and she alleges that the Claimant did not pass this information to the Defendant and did not clarify that this amount would account for future payments anticipated. However, Ms Kurnetzkova had been sent the interim loss adjusters’ report on 13 October 2025 referring to the balance reserve of USD 35 million and the basis for it.
(c) Ms Kurnetzkova criticised the Claimant’s response as incomplete on several occasions without following up with the Claimant to probe further.
(d) Ms Perera provided a thorough analysis in her witness evidence as to why Ms Kurnetzkova’s claims of “insufficient documentation” were not in fact made out, as well as Ms Kurnetzkova’s criticisms that the Claimant “failed to respond to questions raised by the Defendant either at all or within a reasonable time frame”.
(e) The issues raised in Ms Kurnetzkova’s evidence came across, even in totality, as minor queries. She gave evidence that she raised queries both on behalf of Amlin and on her own behalf, wishing to make sure that all the evidence and information in the claims file were in order. However, she accepted that, despite all the queries raised, Amlin ultimately settled all requests to be indemnified under the Amlin Reinsurance, save for the most recent requests for payment. It was not suggested by the Defendant in evidence or in submissions that this was connected to the fact that the Amlin Slip referred to QBE as the “Lead Reinsurer”.
119. I find that the Defendant has failed to satisfy the Court that Liberty’s obligation to indemnify did not arise pursuant to Article 790 of the Qatar Civil Code due to insufficient documentation being provided to substantiate the claims made under the Underlying Insurance (and then the Reinsurance). Further, to the extent relevant, I have already found above that the Underlying Insured’s (and the Claimant’s) cause of action arose upon the loss and not upon the provision of sufficient documentation.
III. Was Liberty 100% likely to pay an indemnity in any event?
120. Article 11 of the Law of Damages and Remedies (applicable to damages under the Contract Law) and Article 27 (applicable to damages for tortious claims under the Law of Obligations) provide as follows:
“(1) Compensation is due only for loss, including future loss, that is established with a reasonable degree of certainty.
(2) Compensation may be due for the loss of an opportunity in proportion to the probability of its occurrence.
(3) Where the amount of damages cannot be established with a sufficient degree of certainty, the assessment is at the discretion of the Court.”
121. The Court must determine the probability of Liberty paying on the claims that have already been settled under the Underlying Insurance and Reinsurance. The Claimant contends that the probability of Liberty paying a claim under the Liberty Retrocession Cover (absent the Cancellation Notice) was 100% because Liberty has already paid under the AON Slip at the reinsurance level, on materially identical wording.
122. Part of the Claimant’s case is that Liberty were the second claims agreement party under the AON Slip, suggesting that Liberty’s decisions to pay under that slip were based on their own analysis of, and agreement with, the coverage position.
123. The Claimant’s position is that this issue meets all the Defences put forward by the Defendant:
(a) There is no evidence that Liberty would have taken any defence relating to the claim not being covered between Doha and the Claimant due to a lack of documentation, or that any alleged lack of documentation provided by the Claimant would have led Liberty to adopt a different attitude to the Liberty Retrocession Cover on the same risk;
(b) In relation to the Defendant’s defence of material non-disclosure, Liberty has been aware through the loss adjuster reports of the previous fire and has yet paid out under the AON Reinsurance.
124. Even if none of the Defendant’s defences are made out, this issue nonetheless has a significant bearing on any declarations which may be issued in the Claimant’s favour for future requests for payment, based on how the proposed declarations were framed by the Claimant at the close of Trial.
125. The Defendant points out that the Claimant’s position is unpleaded and submits as follows:
(a) Liberty’s attitude to the claim was to rely on the most technical defence imaginable - the deemed notice of cancellation - which is “hardly redolent of a reinsurer willing to overlook technical (or substantive) defences”.
(b) Liberty’s participation on the AON Reinsurance was pursuant to an AON binding underwriting authority. This raises different commercial considerations to its participation as sole reinsurer on the Liberty Retrocession, placed differently and through a different broker, the Defendant. AON is one of the world’s most powerful and biggest brokers which can exercise considerable commercial influence and “one would imagine did for a client such as this, Qatar Petroleum, very important in the industry and doubtless a client that generates a very large amount of premium”. Further, even if Liberty were second claims leader on the AON Reinsurance, QBE was the first leader, and Liberty’s position in the Liberty Retrocession Cover was materially different.
(c) Liberty’s outwards reinsurance position on the AON Reinsurance and the Liberty Retrocession is unknown.
(d) There are material discrepancies between the AON Reinsurance and the Liberty Retrocession.
(e) A loss of chance claim is to be assessed at the date of breach and not by reference to subsequent events.
126. By Trial, the Defendant no longer pursued the point that there were material discrepancies between the AON Reinsurance and the Liberty Retrocession Cover, save for the submission that only the AON Reinsurance contained the General Cross-Liability Clause at Section 1, which I have rejected above.
127. Before determining this issue, I must determine, firstly, whether Liberty were the second leader on the AON Slip.
Was Liberty the second leader on the AON Slip?
128. The Defendant relies on the fact that the AON Slip states “The second Lloyd’s syndicate is N/A”. The Defendant’s position is that, because of this wording, Liberty were not formally entitled to be involved in decisions as to whether to pay under the AON Reinsurance, which were to be made by QBE as the leader identified on the AON Slip. The Defendant contends that Liberty may have become involved in such decisions, but were not formally entitled to do so as the second leader.
129. The Claimant submits that, notwithstanding the reference to the second Lloyd’s syndicate being “N/A”, Liberty were the second claims leader under the AON Slip due to the following:
(a) Under “Basis of Claims Agreement”, the AON Slip set out that claims were to be managed in accordance with “The Lloyd’s Claims Scheme (Combined), or as amended or any successor thereto”
(b) The Lloyd’s Claims Scheme (Combined) is now superseded by the Lloyd's Claims Lead Arrangements (“CLA”), which sets out that in a “complex claim”, the managing agent of the leading Lloyd’s Syndicate is to determine the claim in agreement with the managing agent of the second Lloyd’s syndicate.
(c) A “complex claim” under the Combined Scheme and the CLA includes a claim where the amount potentially claimed by the insured from the Lloyd’s syndicates equals or exceeds the sum set out against the relevant risk code. In this case, the risk code was "G", and the relevant sums were GBP 250,000 (Combined Scheme), later revised to GBP 1,000,000 (CLA). In this case, the Lloyd’s syndicates’ share of the potential sum claimed was far in excess of these thresholds (and indeed of all thresholds set out in both schemes).
(d) Therefore, even though the AON Slip states the Lloyd’s second syndicate to be “N/A”, when a claim is large, then – understandably - a second leader will come in to determine the claim in agreement with the managing agent.
(e) In any event, the documentary record indicates that this is how QBE and Liberty operated de facto in determining the claims submitted under the AON Reinsurance.
130. I find that Liberty were the second claims leader on the AON Slip, and accept the Claimant’s submissions that this was the case because of the CLA which superseded the Lloyds’ Claim Scheme (Combined).
131. This is confirmed in an email from AON to the Claimant dated 28 April 2025 which stated:
“Very simply Liberty are the second agreement party on the slip. Due to the amount of the claim, it is customary for the Lloyd’s lead to involve the second syndicate on the slip as an agreement party. A second pair of eyes if you like. This is not unusual”:
132. Even if I were wrong that Liberty were the second claims leader on the AON Slip, in any event AON, Liberty and QBE operated as if Liberty were the second claims leader. There are numerous examples on the documentary record of Liberty either giving approval for a claim, or being asked to give approval, following the presentation of a claim by Doha under the AON Slip.
What is the likelihood that Liberty would pay an indemnity?
133. The Claimant relies upon the following:
(a) Norman Hay Plc v Marsh Limited [2025] EWCA Civ at [28]-[30] which cites Fraser v Furman [1967] 1 WLR 898 (CA). Fraser v Furman was a negligence claim in which the defendant was sued by an employee severely injured from operating a machine in the course of her work for the defendant. The defendant had instructed brokers to procure employee liability insurance, with Eagle Star Insurance Company Ltd. (“Eagle Star”) contemplated as insurers. However, the brokers failed to procure this insurance, with the result that they were sued for breach of contract by the defendant. It was alleged by the brokers that Eagle Star would in any event have been under no liability because of the defendant’s failure to comply with a condition of the policy (the “Condition”). As cited with approval in Norman Hay at [31], Diplock LJ delivering the judgment of the Court of Appeal in Fraser v Furman considered as follows at p.904:
“What damage they have suffered does not depend upon whether Eagle Star would have been entitled as a matter of law to repudiate liability under their standard policy, but whether as a matter of business they would have been likely to do so. What the employers have lost is the chance of recovering indemnity from the insurers. If Eagle Star would not have been entitled to repudiate liability in law, cadit quaestio; the damages recoverable would amount to a full indemnity. Even if they would have been entitled in law, however, to repudiate liability, it does not in my view follow that the employers would be entitled to no damages. The court must next consider in that event, what were the chances that an insurance company of the highest standing and reputation, such as Eagle Star, notwithstanding their strict legal rights, would, as a matter of business, have paid up under the policy.”
(b) The Court of Appeal of England & Wales in Norman Hay also approved the following statement from Jackson on Professional Liability (9th edition) at [16.168] - [16.169] (with emphasis added):
“In assessing the claimant's loss, the court is not strictly concerned with what the insured was entitled to recover under the relevant policy of insurance (where some policy was arranged). Instead, the court has to assess, on the balance of probabilities, what would have occurred had there been no breach of duty by the broker. Consequently, if the court finds that an insurer would or might have made a payment to the claimant but for the broker's negligence, then the claimant will recover damages even if (as a matter of law) the claimant would not have been entitled to any payment from the insurer. The court will assess the likelihood that the claimant would have received a payment from the insurer. If, as a result of the broker's negligence, there is uncertainty as to the claimant's likely recovery from the insurer, then such uncertainty will be resolved in favour of the claimant.”
134. The Defendant submits as follows in relation to the legal principles:
(a) It is important to have regard to the specific Condition which was being addressed by the Court in Fraser v. Furman [1967] 1 WLR 898, which was in the following terms:
“The insured shall take reasonable precautions to prevent accident and disease.”
(b) As the Court of Appeal made clear in Norman Hay v. Marsh [2025] EWCA Civ 58, a case in which no insurance was placed by the broker, the insurer’s liability remains relevant in evaluating the counterfactual:
“That is not to say that the putative insurer’s liability will be irrelevant in evaluating the counterfactual in the event that Norman Hay is able to establish a breach of duty by Marsh. It is a factor which will need to be considered. For example, if it were clear that there would be a valid claim under the putative policy, there would be no need to apply any discount to reflect the uncertainty of recovery. Conversely, if it were clear that there was no valid claim, the case would not reach the standard of a real and distinct, rather than merely negligible, prospect of success which must be shown before assessment of loss of a chance can arise (Perry v Raleys Solicitors at [34]).”
(c) Based on the above passage, the Defendant submits that the loss of chance analysis only comes into play where there is a valid claim under the putative policy, regardless of any defences available to the claim. If there was no cover under the policy, it is not open to a claimant to assert that the putative insurer would have paid that claim ex gratia, because such a loss would not be a foreseeable consequence of the broker’s breach.
(d) The Defendant concedes in its skeleton argument, however, that “the possibility that a reputable insurer would pay a claim by overlooking a purely technical defence would be a foreseeable consequence of the broker’s negligence”. The Defendant submits that the Court should categorise the coverage points and defences which were available to Liberty when assessing the loss of chance claim
Court’s Decision
135. Although this point is unpleaded, I find that the Defendant was not caused prejudice by its late introduction with the Claimant’s skeleton argument (and the Defendant did not allege any such prejudice). The point was a purely legal point, based on the evidence already on the record, and the Defendant was able to respond to the point during the course of the Trial.
136. I accept the Defendant’s submission that Fraser v Furman must be read in context. The Condition of the putative insurance policy relied on in that case was that the employer was required to take “reasonable precautions”. Diplock LJ, delivering the decision of the Court of Appeal, held that a condition should not be construed in a way that is repugnant to the commercial purpose of the contract, and that, in the circumstances of the case, the Condition was not engaged so as to allow the putative insurer to repudiate liability. It could only be engaged if the employer had been “reckless”.
137. However, in any event, as set out at paragraph 133(a) above, Diplock LJ held that the critical question was not whether the insurer was entitled to repudiate liability as a matter of law, but whether they would, as a matter of business, have done so or not (at p.6555). Taking into account a number of factors, including that the onus of proving that the Condition was breached would lie with the insurer; it was arguable that the Condition would not exempt the insurer from liability; the prospect of success was dubious; and there were no cases brought before the court of insurance companies having successfully relied upon the Condition to defeat a claim under an employers’ indemnity policy, Diplock LJ found that:
“…it seems to be highly improbable that, as a matter of business, a company of high reputation, wishing to obtain business, would conceivably take a wholly unmeritorious point in a claim of this kind”.
138. I accept that the general principles set out at Jackson & Powell at paragraph 133(b) above are applicable, and in particular, that:
(a) My task is to determine what would have occurred had there been no breach of duty by the broker, and to assess the likelihood that the Claimant would have received a payment from the insurer;
(b) If there is uncertainty as to the Claimant’s likely recovery from the insurer, then such uncertainty will be resolved in favour of the Claimant.
139. I accept the Defendant’s submission that the loss of chance analysis only comes into play where there is a valid claim under the putative insurance policy. However, I have already dismissed above the Defendant’s argument that there was no prima facie cover under the Underlying Insurance. Further, to the extent relevant, I have found that under Qatar law, the insured’s (and reinsured’s) cause of action arises upon the loss and not upon presentation of the relevant documents to support payment.
140. I find it is irrelevant that Liberty rejected cover under the Liberty Retrocession Cover due to the Cancellation Notice: the effect of the Cancellation Notice was to prevent any policy coming into being for the second year without further agreement between the parties, rather than affording Liberty the opportunity to rely upon a “technical defence”.
141. I accept the Defendant’s point that the AON Reinsurance may give rise to different commercial considerations than the Liberty Retrocession Cover. However, I find it unrealistic to suggest that such considerations would mean that cover would be rejected under the Liberty Retrocession Cover, where cover was accepted under the AON Reinsurance. In fact, the whole prospect of Liberty rejecting cover under the Liberty Retrocession Cover in circumstances where it had already approved payment or paid under the AON Reinsurance has an air of unreality about it.
142. The Defendant did not expand on its point that Liberty’s outwards reinsurance position on the AON Reinsurance and the Liberty Retrocession Cover is unknown, and on how this impacts this issue. The Defendant would presumably argue that different commercial considerations could arise, but again, this does not defeat my firm view that the prospect of Liberty rejecting cover under the Liberty Retrocession Cover in circumstances where it had already approved or paid under the AON Reinsurance is completely unrealistic.
143. In Fraser v Furman, Diplock LJ referred to Eagle Star as “an insurance company of the highest standing and reputation” and considered it highly improbable that such a “company of high reputation, wishing to obtain business” would take a wholly unmeritorious point to decline cover. Likewise, considering that Liberty is a well-known and reputable insurer, wishing to continue to attract business, I do not consider it likely or even plausible that Liberty would accept cover under the AON Reinsurance yet – entirely inconsistently - decline cover under the Liberty Retrocession Cover (in the same material terms) for any of the reasons advanced by the Defendant (none of which were raised by any of the other insurers involved in the insurance scheme). I assess the commercial likelihood of this as nil, for all practical purposes.
144. In relation to the Defendant’s submission that a loss of chance claim is to be assessed at the date of breach and not by reference to subsequent events, the Court did not have the benefit of any submissions from either the Defendant or the Claimant on how this principle may apply (or not apply) in the present circumstances, beyond the Defendant’s bare submission.
145. The Court observes that the principle that “the court should never speculate where it knows” (per Harman LJ in Curwen v James [1963] 1 WLR 748) has become a cornerstone of the law of damages for breach of contract, not just in England and Wales but in other common law jurisdictions. This principle may displace the general rule that damages are to be assessed on the date of breach, as the latter is not an absolute rule and is subject to the overriding compensatory principle (see, for example, Golden Strait Corporation v Nippon Yusen Kubishika Kaisha [2007] UKHL 12 per Lord Scott of Foscote at [35]-[36], and iVenture Card Limited & Ors v Big Bus Singapore City Sightseeing Pte Ltd & Ors [2021] SGCA 97 at [137]). Assessing the Claimant’s damages for breach of contract, the Claimant is entitled to be put in the position it would have been in had the Defendant not been in breach, and I find that the Court may take into account subsequent events when assessing the Claimant’s loss of chance.
146. For the reasons set out above, I assess the likelihood of the following at the highest possible level of certainty:
(a) Liberty would have paid out under the Liberty Retrocession Cover for all claims already paid out under the AON Reinsurance, for which it was the second loss leader; and that
(b) Liberty would pay out under the Liberty Retrocession Cover for future claims which it has agreed to pay out under the AON Reinsurance.
147. For the purposes of an assessment of damages due to the Claimant, this translates to the Claimant being entitled to be indemnified for 100% of the claims that it would have submitted to Liberty under the Liberty Retrocession Cover, where Liberty has already agreed to pay out for those claims under the AON Reinsurance. Where Liberty has already paid out for claims under the AON Reinsurance, this carries an implicit assumption that it has agreed to pay out for those claims.
IV. Would Liberty have been prevented under Qatar law from taking an inconsistent position between the AON Slip and the Liberty Retrocession?
148. The Claimant argues that, under Articles 172 and 776 in conjunction with 790 of the Qatar Civil Code, where QBE exercised claims control, QBE became the legal decisionmaker regarding documentation sufficiency and all parties in the chain are bound by those determinations under good faith principles, absent fraud or manifest error. The Defendant disagrees with the Claimant’s legal analysis under Qatar law, and points out that it fails to see how Liberty could be bound by a claims control clause in a different contract of reinsurance which contained a different contractual chain to that in which it assumed risk.
149. Given my finding at III. above, this issue no longer arises for determination.
V. Would Liberty have been entitled to charge more premium or void the policy based on the previous AC unit fire?
150. The Defendant’s case on material non-disclosure also does not arise based on my finding at III. above. I am mindful that Liberty has not raised the issue of material non-disclosure under the AON Reinsurance, and in fact none of the insurers involved in the insurance scheme in this case have raised this point, even though they have been aware through loss adjuster reports of the previous fire at the Superyacht Hall caused by an AC unit. This may be because, as argued by the Claimant, the fire was minor and extinguished promptly. In any event, I do not need to make a finding on this point.
151. The Defendant accepts that neither QBE nor Liberty have taken this point to date, but asserts that they may well do so going forward, and that they will be informed of this point depending on the outcome of this trial.
152. Should Liberty take the “material non-disclosure” point under the AON Reinsurance at any point, then the parties are at liberty to return to Court to seek relief for any consequences that this may have on how liability has been determined in this case.
However, as matters stand, this issue does not arise.
153. On the basis of the matters set out above, the Court dismisses the Defendant’s application to admit the expert report of its appointed underwriting expert Mr Hanna as to the additional premium that would have been justified on the basis of the alleged material non-disclosure.
F. REMEDIES AND INTEREST
Monetary Award
154. The Claimant claims in these proceedings:
(a) QAR 6,089,712.01, comprising half of the Claimant’s 10% share of HOC1; and
(b) QAR 146,724.61, comprising half of the Claimant’s 10% share of HOC2 (which continues to accrue).
155. The Claimant has helpfully set out in a table references to the underlying quantum documents on the documentary record, which have not been disputed by the Defendant. Each payment has been expressly approved by QBE, or QBE and Liberty, and I accept that where QBE has approved a payment, this has been with (or is subject to) Liberty’s approval (indeed, one of the emails from the QBE Claims Adjuster states “I hereby agree for funds to be released to [Doha], subject to second agreement parties approval”).
156. For HOC2, the Claimant’s claim has increased since the Amended Particulars of Claim was filed, on account of further payments made by the Claimant in respect of HOC2. Having reviewed the credit notes issued by the Claimant to Doha in respect of all payments made in respect of HOC2, the total value of the 4 payments made is QAR 293,449.21. The Defendant’s half share of these payments is USD 146,724.61.
157. I find that the Claimant is entitled to the sums it claims as set out at paragraph 154 above.
Interest
158. In respect of its monetary claims, the Claimant seeks compound interest pursuant to Article 18 of the Law of Damages and Remedies and Articles 118 and 119 of the Contract Law at a rate of 9% from the dates on which the Claimant made payments in respect of HOC1 and HOC2. The dates from which interest is claimed in the Amended Particulars of Claim are as follows:
(a) from 7 October 2020 for half the Claimant’s payment in respect of HOC1, in the sum of QAR 6,089,712.01;
(b) from “a date to be determined” for half the Claimant’s payment of the first sum in respect of HOC2 of QAR 87,541.13;
(c) from 3 September 2024 for half the Claimant’s payment of the second sum in respect of HOC2 in the sum of QAR 17,481; and
(d) from “a date to be determined” for half the Claimant’s payment of the third sum in respect of HOC2 of QAR 4,278.
159. The Defendant only took issue with the interest claimed on the Claimant’s payment in respect of HOC1, arguing that as this was the first claim in respect of the Loss, it would be reasonable for Liberty to have taken some time to consider the claim commercially before paying. The Defendant accordingly submitted that interest should run from 7 December 2020. No submissions were made against this point by the Claimant, and I accept that interest on the sum awarded to the Claimant in respect of HOC1 should run from 7 December 2020.
160. It is difficult for the Court to issue final orders in respect of interest for the Defendant’s half of the first and third sums paid in respect of HOC2 by the Claimant, as the date from which interest should run for those sums remains to be determined. The documentary record includes the credit notes for each payment made by the Claimant to Doha in respect of HOC1 and HOC2. However, the date of the credit note for the Claimant’s HOC1 payment, and that for the Claimant’s payment of the second sum in respect of HOC2, do not tally with the date from which the Claimant claims interest (for example, the date of the credit note for the Claimant’s payment in respect of HOC1 is 31 October 2020, and the Claimant has submitted that the date of payment is 7 October 2020).
161. The Claimant will be invited to make further submissions on the dates from which interest should run for all four of its payments in respect of HOC2, with the Defendant having an opportunity to reply. The interest due for the Defendant’s half of the Claimant’s payments made so far in respect of HOC2 may then be the subject of a further Court order.
Declarations
162. At Trial, the parties made submissions as to the appropriate form of the declarations sought by the Claimant. There was no dispute that under Article 790 of the Qatar Civil Code, payment under the putative Liberty Retrocession Cover would need to be made upon the submission of sufficient documentation, and the original declarations sought by the Claimant did not provide for this step.
163. The only dispute between the parties on the Claimant’s proposal as to the appropriate form of declaration was whether the declaration should provide for the Claimant to be indemnified by the Defendant for payment of an invoice in respect of HOC2 or HOC3 where Liberty “has paid or agreed to pay that invoice” (as argued by the Claimant) or simply where Liberty has paid that invoice (as argued by the Defendant). Given that payment may be made by way of set-off, the Defendant proposed the alternative wording “where Liberty has allocated or transferred funds in respect of that invoice”. I was persuaded by the Claimant that they would not be able to compel documents from Liberty showing funds leaving an account, or any set-off, and that the broader wording proposed by the Claimant provided a greater chance of proving agreement to pay by Liberty.
164. For the avoidance of doubt, where Liberty “has paid or agreed to pay that invoice”, this refers to Liberty’s payment of, or agreement to pay, its share under the AON Reinsurance of the underlying invoice settled by Doha under the Underlying Insurance.
165. The final wording of the declarations which have been ordered provides for the Claimant to be entitled to be indemnified by the Defendant for the Defendant’s half share of any invoice paid by the Claimant in respect of HOC2 or HOC3.