September 15, 2023 COURT OF FIRST INSTANCE - ORDERS
Claim No. CFI 100/2021
THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS
IN THE COURT OF FIRST INSTANCE
BETWEEN
GHAM 2 LIMITED
Claimant
and
(1) MR AJAY BHATIA
(2) TIYA HOLDINGS LIMITED
(3) SOL INTERNATIONL PROPERTIES LIMITED
Defendants
FINAL COSTS CERTIFICATE OF THE ASSISTANT REGISTRAR DELVIN SUMO
UPON the Order with Reasons of H.E. Justice Maha Al Mheiri dated 26 April 2023
AND UPON the Defendant’s Notice of Commencement of Assessment of Bill of Costs dated 26 July 2023 (the “Bill of Costs”)
AND UPON the Claimant’s Points of Dispute to the Bill of Costs dated 15 August 2023 (the “Points of Dispute”)
AND UPON the Defendant’s Reply to the Points of Dispute dated 5 September 2023 (the “Reply to the Points of Dispute”)
AND PURSUANT TO Part 38 and Part 40 of the Rules of the DIFC Courts (“RDC”)
IT IS HEREBY ORDERED THAT:
1. The Claimant shall pay to the Defendants a total of AED 335,946.76 (the “Amount”) within 21 days from the date of this Costs Certificate, comprising:
(a) AED 312,508.60 in respect of the Defendants’ costs in the course of these proceedings including the costs assessment proceedings; and
(b) AED 23,438.16 in respect of the fee paid by the Defendants for commencement of the costs assessment proceedings.
2. In the event the Claimant fails to pay the Amount within 21 days from the date of this Costs Certificate, Post Judgment interest, pursuant to Practice Direction No. 4 of 2017 (Interest on Judgments), will accrue on the Amount at the rate of 9% per annum from the end of the 21-day period stated in paragraph 1 of this Costs Certificate until the date of full payment.
Issued by:
Delvin Sumo
Assistant Registrar
Date of issue: 15 September 2023
At: 3pm